Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SAMAR 2ND DEO Award a ₱9.6M contract to PYUKEI CONSTRUCTION INC.National agencies
Transaction hash:
ce4bde549549b88b63da502717e1e4a520979cf60c21d21c44d0fd7e4528cb4a
Status:
Included and unchanged
Block:
#4,067 1,946 blocks after it
Position in block:
Transaction 73 of 85
Award day:
Mar 30, 2020 (6 yrs 7 mo ago)
Value:
₱9,615,485.15
Project:
20IK0070
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #4,067 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Regular Infra - GAA 2020 LP", i.e. the FY2020 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SAMAR 2ND DEO awarded it to PYUKEI CONSTRUCTION INC. on 2020-03-30.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 20IK0070: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2020-11-15). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored ce4bde5495…28cb4anow …
- 2. Block Merkle root changedstored 3754f0aab7…c07eefnow …
- 3. Block #4067 hash changedstored b67c7489c0…1591ecnow …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (7 steps)
How this one record is tied to the block's Merkle root, without needing the other 84 records. Each step hashes the current value together with the sibling shown.
- leaf ce4bde549549b88b63da502717e1e4a520979cf60c21d21c44d0fd7e4528cb4a
- 01 L ccb0a32777149d99d1fdf4f4197d8d081748cd62eae062d8d7f2d5e144844c2a
- 02 R d6c4bacae89e9337bc144d7ecb8b7a5a2ff2869ae74eb497bdb0bb3bbc101901
- 03 R 4bb939490a0440b9802d09fc90f88800bf5d46203aadfe6c21863abede5b44db
- 04 L 70a6ddcf4156cfd0bed27e90415704218a8a60327e60f545c17141f1a5a8f536
- 05 R 58763eae948e45be603e7a21d78d7d96289e4c7150624f43cb1b61937d9e9902
- 06 R 18fe55b780de2eef2cf5abbc92f316bf8b3149a534b0b037f82e7d9127fafa2f
- 07 L 10d68b34eda3d25581ae3c2be027b387b499a22bcb0fddde633e4f845847f0aa
- root 3754f0aab7dd76915ca6d34d65109890c98f14532c9e5b0b04ccf7647cc07eef