DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PALAWAN 3RD DEO Award a ₱6.9M contract to DON VIRGILIO BUILDERS AND SUPPLYNational agencies
Transaction hash:
d2a99b8b9c4a72d836db6a6b8e126a2d573550df8d4d05a5ebaade785ea93fc0
Status:
Included and unchanged
Block:
#4,547 1,466 blocks after it
Position in block:
Transaction 213 of 265
Award day:
Aug 24, 2021 (5 yrs 2 mo ago)
Value:
₱6,939,524.63
Project:
21EG0084-Concreting of Sitio Tagbariri,
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #4,547 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Outside Infra - GAA 2021 DA FMR", i.e. the FY2021 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PALAWAN 3RD DEO awarded it to DON VIRGILIO BUILDERS AND SUPPLY on 2021-08-24.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 21EG0084: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2021-12-10). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored d2a99b8b9c…a93fc0now …
- 2. Block Merkle root changedstored 755cbad556…46d8banow …
- 3. Block #4547 hash changedstored 1284309cef…3e3763now …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (9 steps)
How this one record is tied to the block's Merkle root, without needing the other 264 records. Each step hashes the current value together with the sibling shown.
- leaf d2a99b8b9c4a72d836db6a6b8e126a2d573550df8d4d05a5ebaade785ea93fc0
- 01 L d0950652e11362fb378808ef214c8bf6f711c468a003358ec5f648e0d45c1096
- 02 R 6a93c2957a5e97dde62a06923150611eaf123be0560d77115756bcda3582bbe1
- 03 L 1577328303a660e70b03bd0ae80f312cc33d306e249ff07fce0a511abd99d4b7
- 04 R 713b13fae056886e8306c3ddf1fc4e6e939d74b21da6c5f9977cfce899703f36
- 05 L 57c67dec2e2a56a4d82c37fe496a06cd94a36aaa3f8b68a75081c134264fc03b
- 06 R 14fad1bfe46352a072a664e09396ee3aa1f78f697cd2a3a8bdc56e3a5f0da9cd
- 07 L 783f3b824568532d2a5cdf7715f42eb6ed7c834d9094063da04ec57f2a31e977
- 08 L 32695a6eaa5d91cbbdcdf31df1b8ebfd44788a0ef54e6c8dd07090ee57731c5e
- 09 R a2a8d9a7a5f2f2fd9d5e67a4b0d204a67472ce2632f923b36bc654e0bfb0d392
- root 755cbad556c49c943846c5df7e57e4734d3e15e284d2fe2a2e3010020246d8ba