DPWH SOUTH COTABATO II-DISTRICT ENGINEERING OFFICE Award a ₱15.9M contract to J.G. ORANZA CONSTRUCTIONNational agencies

Transaction hash:
d4324e0bad9c7c6cf74c6b260b9bce3778f26354656149bbf393a12cea1fec3b
Status:
Included and unchanged
Block:
#2,869 3,144 blocks after it
Position in block:
Transaction 130 of 153
Award day:
Oct 5, 2016 (10 yrs 1 mo ago)
Value:
₱15,882,580.71
Project:
16MB0024(Republished) Completion of SC 2nd DEO

Accountability

Bill Sec. 3 and 19
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #2,869 signature valid Demo key, proves nothing about the governmentPublic key

Linked records: from budget to payment

Bill Sec. 5
  1. 1. Appropriation
    GAA line item · Sec. 5(b)
    DPWH lists the funding source as "Regular Infra - GAA 2016 Locally Funded Projects", i.e. the FY2016 GAA. The exact UACS line is not given.
    Partly
  2. 2. Allotment release
    SARO / allotment · Sec. 5(c)(iii)
    Not published per project. DBM releases SAROs, but not linked to individual contracts.
    Not published
  3. 3. Cash allocation
    Notice of Cash Allocation · Sec. 5(c)(iv)
    Not published per project.
    Not published
  4. 4. Contract award
    Notice of Award (PhilGEPS) · Sec. 5(d)
    DPWH SOUTH COTABATO II-DISTRICT ENGINEERING OFFICE awarded it to J.G. ORANZA CONSTRUCTION on 2016-10-05.
    Found
  5. 5. Contract & progress
    Contract / progress report (DPWH) · Sec. 5(d)
    DPWH contract 16MB0024: Completed, 100% physical progress.
    Found
  6. 6. Payment
    Disbursement voucher · Sec. 5(c)(viii)
    Not published. No public source shows how much of this contract has been paid.
    Not published
  7. 7. Completion
    Certificate of completion · Sec. 5(d)
    DPWH marks the contract "Completed" (end 2017-04-10). The certificate itself is not published.
    Partly
  8. 8. Audit
    COA annual audit report · Sec. 5(e)(iii)
    No COA finding linked to this contract.
    Not published

2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.

Tamper test: try changing this record

Demo

Edit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.

  1. 1. Record fingerprint changed
    stored   d4324e0bad…1fec3bnow      …
  2. 2. Block Merkle root changed
    stored   ed4e29126e…b4993dnow      …
  3. 3. Block #2869 hash changed
    stored   0416021660…81f932now      …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.

Merkle proof (8 steps)

How this one record is tied to the block's Merkle root, without needing the other 152 records. Each step hashes the current value together with the sibling shown.

  1. leaf  d4324e0bad9c7c6cf74c6b260b9bce3778f26354656149bbf393a12cea1fec3b
  2. 01 R d5849f9e0b8646a7c69719fde6f2ee5f3491f956484b6a30dad04b007a010ca9
  3. 02 L 9e6e24693b1d27134aed950d889ae2d7986fc8bdc9408593d07045341768293e
  4. 03 R 221167ddae8256674203b91a79622d790565911c05ceca66b27e0cd221ac454c
  5. 04 R f0892f67eadedd6922a07a2a040f96904bc95d6a346961ecb8f302a216906b99
  6. 05 R c1a00cf91af761b82331e8837f80e130a948236979763b8d752f191b1595d348
  7. 06 R 05abda023f4268763a5fc9d5539ca6e62214ef7d731b244959971dd78b7a20a9
  8. 07 R d689506c151739a3f73b7be92129b738654289a2a4ca1d9ba493fbf8005b2208
  9. 08 L 3e7f665c884f34f0e4d60796a032711cc2efef67dcc03582bd1183f79d32575a
  10. root  ed4e29126eaeaefca5550cf362f74c54eabb6206976d34c4c4c9e2519fb4993d