FY2026 GAA: ₱6.79T
PisoScan
DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works

Transaction details

API
Transaction hash:
da6e1da264be028ff733fbce952023cba1d899bb6a8a2163c203ebe715265013
Status:
Included and unchanged
Block:
#4,398 1,615 blocks after it
Position in block:
Transaction 266 of 302
Award day:
Mar 23, 2021 (5 yrs 7 mo ago)
Value:
₱19,302,303.46
Project:
20CC0301–Concreting of Brgy. Talampas to Brgy. Cam

Accountability

Bill Sec. 3 and 19
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #4,398 signature valid Demo key, proves nothing about the governmentPublic key

Linked records: from budget to payment

Bill Sec. 5
  1. 1. Appropriation
    GAA line item · Sec. 5(b)
    DPWH lists the funding source as "Outside Infra - R.A. 11494 DA FMR 2020". The exact UACS line is not given.
    Partly
  2. 2. Allotment release
    SARO / allotment · Sec. 5(c)(iii)
    Not published per project. DBM releases SAROs, but not linked to individual contracts.
    Not published
  3. 3. Cash allocation
    Notice of Cash Allocation · Sec. 5(c)(iv)
    Not published per project.
    Not published
  4. 4. Contract award
    Notice of Award (PhilGEPS) · Sec. 5(d)
    DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 1ST DEO awarded it to C & F CONSTRUCTION AND DEVELOPMENT CORPORATION on 2021-03-23.
    Found
  5. 5. Contract & progress
    Contract / progress report (DPWH) · Sec. 5(d)
    DPWH contract 20CC0301: Completed, 100% physical progress.
    Found
  6. 6. Payment
    Disbursement voucher · Sec. 5(c)(viii)
    Not published. No public source shows how much of this contract has been paid.
    Not published
  7. 7. Completion
    Certificate of completion · Sec. 5(d)
    DPWH marks the contract "Completed" (end 2021-06-17). The certificate itself is not published.
    Partly
  8. 8. Audit
    COA annual audit report · Sec. 5(e)(iii)
    No COA finding linked to this contract.
    Not published

2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.

Tamper test: try changing this record

Demo

Edit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.

  1. 1. Record fingerprint changed
    stored   da6e1da264…265013now      …
  2. 2. Block Merkle root changed
    stored   385a9af342…1e1a17now      …
  3. 3. Block #4398 hash changed
    stored   87938c6a3d…5a36c7now      …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.

Merkle proof (9 steps)

How this one record is tied to the block's Merkle root, without needing the other 301 records. Each step hashes the current value together with the sibling shown.

  1. leaf  da6e1da264be028ff733fbce952023cba1d899bb6a8a2163c203ebe715265013
  2. 01 R daa06eece0ba578ea1fbe6de279839f7be3907e9672128f616fe78be1cb8f693
  3. 02 L 7b1b154fac126a8768a4aaf02634aef6ab8c93f3ea3aa5f87a6860c3171b8275
  4. 03 R 4b91fc348fbc7b612355682594a82395907761a0abe1fe6322e3d250090b815c
  5. 04 L 8f6c5e37d8eb541ab4af81c079f79a4aafd8661f4c49b5d0f0547a134d14cf9d
  6. 05 R 34e8362db9c9575202774cc7d9f9618df71afe34d51289e950870482587401f9
  7. 06 R c80a19f4f3b595418b94d636cc3840d2440509d27567bc6e5521ac426cf38752
  8. 07 R ed282c4bff4743ea64640a720693f525465e9405380616e6bcf8fa975329502c
  9. 08 R 50502ee5031ce551b9e59544fcf76ac79787246cc99d902fa32cd33ed904d3c3
  10. 09 L 4ad77633d5a17175ccf546a5935cbda2ed6ce808abfd1db07748eca1e72a4956
  11. root  385a9af34211ccdc1deb2ab2647308770ae7557e0110e6cf8bc28d1b391e1a17