Skip to content
FY2026 GAA: ₱6.79T
PisoScan
DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works

Transaction details

API
Transaction action

PROVINCE OF ORIENTAL MINDORO Award a ₱984.6K contract to NAMNAMA CONSTRUCTION SUPPLIESProvinces

Transaction hash:
e39835c50ea72f30f7f93bea527cf6ecf960afd0baef6a996682170edec7f1bc
Status:
Included and unchanged
Block:
#3,746 2,267 blocks after it
Position in block:
Transaction 12 of 16
Award day:
Apr 26, 2019 (7 yrs 6 mo ago)
Value:
₱984,574.41
Project:
Construction of River Control at Sitio Wawan, Brgy

Accountability

Bill Sec. 3 and 19
Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #3,746 signature valid Demo key, proves nothing about the governmentPublic key

Linked records: from budget to payment

Bill Sec. 5
  1. 1. Appropriation
    GAA line item · Sec. 5(b)
    The award does not say which budget line pays for it.
    Not published
  2. 2. Allotment release
    SARO / allotment · Sec. 5(c)(iii)
    Not published per project. DBM releases SAROs, but not linked to individual contracts.
    Not published
  3. 3. Cash allocation
    Notice of Cash Allocation · Sec. 5(c)(iv)
    Not published per project.
    Not published
  4. 4. Contract award
    Notice of Award (PhilGEPS) · Sec. 5(d)
    PROVINCE OF ORIENTAL MINDORO awarded it to NAMNAMA CONSTRUCTION SUPPLIES on 2019-04-26.
    Found
  5. 5. Contract & progress
    Contract / progress report (DPWH) · Sec. 5(d)
    No matching DPWH contract record (only DPWH contracts are listed with progress).
    Not published
  6. 6. Payment
    Disbursement voucher · Sec. 5(c)(viii)
    Not published. No public source shows how much of this contract has been paid.
    Not published
  7. 7. Completion
    Certificate of completion · Sec. 5(d)
    No completion certificate published.
    Not published
  8. 8. Audit
    COA annual audit report · Sec. 5(e)(iii)
    COA's CY2024 audit of Oriental Mindoro gave a "qualified" opinion on its financial statements (not specific to this contract).
    Partly

1 of 8 documents found, 1 partly. Under CADENA every step would be published within 7 working days and linked to this record.

Tamper test: try changing this record

Demo

Edit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.

  1. 1. Record fingerprint changed
    stored   e39835c50e…c7f1bcnow      …
  2. 2. Block Merkle root changed
    stored   d44a7a0fe2…336296now      …
  3. 3. Block #3746 hash changed
    stored   0b4bfba879…2442benow      …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.

Merkle proof (4 steps)

How this one record is tied to the block's Merkle root, without needing the other 15 records. Each step hashes the current value together with the sibling shown.

  1. leaf  e39835c50ea72f30f7f93bea527cf6ecf960afd0baef6a996682170edec7f1bc
  2. 01 R ecdc6b11e06c1db7e8ac57f5925e86e1526576f89697d1cc4350e91be455e62c
  3. 02 R 479d10ab96a84b5914e835472e5f3b2f4d4ce9c3e3882d4d45d26324c1ab671a
  4. 03 L da5c18452f8963e6fb495378107290d6cd1f4520ecf0231a5be34f13274d7078
  5. 04 L a6da8748b9958a874e7061167942056cca9b8a9ef4693826ec904710c8ec8a81
  6. root  d44a7a0fe2783eb601a3bba641660c5e70943c33d1101e7a3ef0b248bd336296