Transaction details
APITransaction action
MUNICIPALITY OF GUBAT, SORSOGON Award a ₱1.4M contract to R JARABO CONSTRUCTION AND SUPPLIESMunicipalities
Transaction hash:
e53dbc10a63b34644e24e794073b29a2091d415d91f32e154b3540eb4d5ffb41
Status:
Included and unchanged
Block:
#5,102 911 blocks after it
Position in block:
Transaction 451 of 501
Award day:
Mar 24, 2023 (3 yrs 7 mo ago)
Value:
₱1,398,405.91
Project:
Construction Project
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #5,102 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)The award does not say which budget line pays for it.Not published
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)MUNICIPALITY OF GUBAT, SORSOGON awarded it to R JARABO CONSTRUCTION AND SUPPLIES on 2023-03-24.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)No matching DPWH contract record (only DPWH contracts are listed with progress).Not published
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)No completion certificate published.Not published
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)COA's CY2024 audit of Gubat gave a "unmodified" opinion on its financial statements (not specific to this contract).Partly
1 of 8 documents found, 1 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored e53dbc10a6…5ffb41now …
- 2. Block Merkle root changedstored f0c0ccf3e8…9ff69cnow …
- 3. Block #5102 hash changedstored 2cfcebce7d…ea884anow …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (9 steps)
How this one record is tied to the block's Merkle root, without needing the other 500 records. Each step hashes the current value together with the sibling shown.
- leaf e53dbc10a63b34644e24e794073b29a2091d415d91f32e154b3540eb4d5ffb41
- 01 L e51571708dbac40b5557b6ab99f3bb5187742835616bfbc3fe9a05e3131e078a
- 02 L d918d2e272924071f8c2a3d91fd1982d6e0fae86fdd1fc15a4e65c2490b5c9fe
- 03 R e9e6d39a05edd8bf6af9c39fa6c3aba38646f9f53dd2152019baa45729fd21e7
- 04 R efeafb11e9fe37b1fb1275098f5596a3cfba260b77c7afbdcebe5a0aad6d82d9
- 05 R 6e2c35cde896f4da8a11b76694ec38b813abc1c8311e7728ea7dac963ac3ef27
- 06 R 49f341767af92eb909e8b86ebc36a2282805c563f9fb06c68b553ff0a6ef82c2
- 07 L c121027ea2d27721db8834fdd1678caf301b97af32ab0fbfcb82e6ae0750c2cb
- 08 L 8242aaf9e66147d660d5e4f111124440b67863e9b2acdd788f704f4c98a70a1d
- 09 L fb532b636d237b63716abd5b267f29b8fd8aaee0f1049f0c4c2f169ee32a2b34
- root f0c0ccf3e8c5de5f287ac26fc7caf1a7a3204cd8dfa203d1d3087254f49ff69c