FY2026 GAA: ₱6.79T
PisoScan
DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works

Transaction details

API
Transaction action

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CARAGA Award a ₱91.4M contract to VICENTE T. LAO CONSTRUCTIONNational agencies

Transaction hash:
e6a3a871e4d9af8624a0b89a54d4495cb00628f998d303c2c347ef1247dada4b
Status:
Included and unchanged
Block:
#3,058 2,955 blocks after it
Position in block:
Transaction 182 of 201
Award day:
Apr 26, 2017 (9 yrs 6 mo ago)

Accountability

Bill Sec. 3 and 19
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #3,058 signature valid Demo key, proves nothing about the governmentPublic key

Linked records: from budget to payment

Bill Sec. 5
  1. 1. Appropriation
    GAA line item · Sec. 5(b)
    DPWH lists the funding source as "Regular Infra - GAA 2017 MFO-1", i.e. the FY2017 GAA. The exact UACS line is not given.
    Partly
  2. 2. Allotment release
    SARO / allotment · Sec. 5(c)(iii)
    Not published per project. DBM releases SAROs, but not linked to individual contracts.
    Not published
  3. 3. Cash allocation
    Notice of Cash Allocation · Sec. 5(c)(iv)
    Not published per project.
    Not published
  4. 4. Contract award
    Notice of Award (PhilGEPS) · Sec. 5(d)
    DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CARAGA awarded it to VICENTE T. LAO CONSTRUCTION on 2017-04-26.
    Found
  5. 5. Contract & progress
    Contract / progress report (DPWH) · Sec. 5(d)
    DPWH contract 17N00049: Completed, 100% physical progress.
    Found
  6. 6. Payment
    Disbursement voucher · Sec. 5(c)(viii)
    Not published. No public source shows how much of this contract has been paid.
    Not published
  7. 7. Completion
    Certificate of completion · Sec. 5(d)
    DPWH marks the contract "Completed" (end 2018-06-24). The certificate itself is not published.
    Partly
  8. 8. Audit
    COA annual audit report · Sec. 5(e)(iii)
    No COA finding linked to this contract.
    Not published

2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.

Tamper test: try changing this record

Demo

Edit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.

  1. 1. Record fingerprint changed
    stored   e6a3a871e4…dada4bnow      …
  2. 2. Block Merkle root changed
    stored   b3226bfe12…9f788enow      …
  3. 3. Block #3058 hash changed
    stored   bf1fb71800…1fb65bnow      …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.

Merkle proof (8 steps)

How this one record is tied to the block's Merkle root, without needing the other 200 records. Each step hashes the current value together with the sibling shown.

  1. leaf  e6a3a871e4d9af8624a0b89a54d4495cb00628f998d303c2c347ef1247dada4b
  2. 01 R e914cdd81a56cb0845471102def2ca0d7ee1631e59d3a57c497766aea566fc27
  3. 02 L 183165057d2a6e7940bc64ace5a7a1c938a13a4c2700059ec94c202144cd757a
  4. 03 L a88acee93fc19beb3c4bb9e3fe74cfd9b58f7cc60b0d8745590394eaa337bfaa
  5. 04 R afa78c0c534a31df48904bec6d4ffd10b8b017219192416321f5854503fd6d34
  6. 05 L 29b28b86d67fbadce58c3c008fb8772b7c371445ef11e2e31cce8d89f892b384
  7. 06 L c3840fecc659f35d99c90ffc4e5f85def8a9529d655c4de102cbee74a14ad827
  8. 07 R bb4001e3f23a17e7f0e85d89c7e9befc61a72ba7f5298f397a6229a8593ba883
  9. 08 L 2ee1d98763df5bbe36347e4de00a04bae73f4cdc5d72d6a13b437f50581e94e1
  10. root  b3226bfe1214b17b3c70cf92aa29a3514948c41abc9ce5830a858639809f788e