DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NEG. OCC. 3RD DEO Award a ₱34.8M contract to ALMANA CONSTRUCTION AND DEV'T CORPORATIONNational agencies
Transaction hash:
e8c8ed375a38518d1f6453e2da0f78429585355ed85baa1086f3a6e88226847a
Status:
Included and unchanged
Block:
#4,115 1,898 blocks after it
Position in block:
Transaction 152 of 166
Award day:
May 27, 2020 (6 yrs 5 mo ago)
Value:
₱34,836,280.69
Project:
20GM0062
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #4,115 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Outside Infra - GAA 2019 NDRRMF", i.e. the FY2019 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NEG. OCC. 3RD DEO awarded it to ALMANA CONSTRUCTION AND DEV'T CORPORATION on 2020-05-27.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 20GM0062: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2021-11-02). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored e8c8ed375a…26847anow …
- 2. Block Merkle root changedstored 0b0d35c987…9e74dbnow …
- 3. Block #4115 hash changedstored 2d25ca8918…9a26d7now …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (8 steps)
How this one record is tied to the block's Merkle root, without needing the other 165 records. Each step hashes the current value together with the sibling shown.
- leaf e8c8ed375a38518d1f6453e2da0f78429585355ed85baa1086f3a6e88226847a
- 01 R ea54a475ad7eefbf0f96a81735e9ea0e43893ded824b3d8e78e817ab8ec6562a
- 02 R 8e947e9b8a81f72b487fb72ea3c771b095560e158af40b5650c02e21b72d325c
- 03 R ff10f44787baab669fe619b080e8cff229eebaa94793f067fdd791dcb8017e53
- 04 L 478edcbc45c3128416b8b95d67dba63fc32aaf1feb2177024f501aace6688496
- 05 L 4f5c886226b055292e29d75c3c4be7c5c44893f5a28cd6ad5962e9edcdfb441c
- 06 R 5cbba2fb01aded469d4d4a8f469dcfa9d7660cdaf363ecbd6a88e37149039c9a
- 07 R 7201618b29ad447406cda2a1a31b352f3ed090f2a8fb23a6cf5f7c2866d0c5b2
- 08 L 4a42f5ebda28548db2cc731171ae0c785e0275943e93d6398ec1aac4a2659f23
- root 0b0d35c987964167ba663ae3e37a77f2d7ea7b84e62720542b9babdd619e74db