Skip to content
FY2026 GAA: ₱6.79T
PisoScan
DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works

Transaction details

API
Transaction action

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES NORTE ED Award a ₱12.1M contract to MPT CONSTRUCTIONNational agencies

Transaction hash:
eada2c1f5b1ab08637313724d1d82db66f5d96d31c9df62a695685a8b45f23a1
Status:
Included and unchanged
Block:
#4,472 1,541 blocks after it
Position in block:
Transaction 217 of 234
Award day:
Jun 7, 2021 (5 yrs 5 mo ago)

Accountability

Bill Sec. 3 and 19
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #4,472 signature valid Demo key, proves nothing about the governmentPublic key

Linked records: from budget to payment

Bill Sec. 5
  1. 1. Appropriation
    GAA line item · Sec. 5(b)
    DPWH lists the funding source as "Outside Infra - GAA 2021 DA FMR", i.e. the FY2021 GAA. The exact UACS line is not given.
    Partly
  2. 2. Allotment release
    SARO / allotment · Sec. 5(c)(iii)
    Not published per project. DBM releases SAROs, but not linked to individual contracts.
    Not published
  3. 3. Cash allocation
    Notice of Cash Allocation · Sec. 5(c)(iv)
    Not published per project.
    Not published
  4. 4. Contract award
    Notice of Award (PhilGEPS) · Sec. 5(d)
    DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES NORTE ED awarded it to MPT CONSTRUCTION on 2021-06-07.
    Found
  5. 5. Contract & progress
    Contract / progress report (DPWH) · Sec. 5(d)
    DPWH contract 21FC0139: Completed, 100% physical progress.
    Found
  6. 6. Payment
    Disbursement voucher · Sec. 5(c)(viii)
    Not published. No public source shows how much of this contract has been paid.
    Not published
  7. 7. Completion
    Certificate of completion · Sec. 5(d)
    DPWH marks the contract "Completed" (end 2022-09-27). The certificate itself is not published.
    Partly
  8. 8. Audit
    COA annual audit report · Sec. 5(e)(iii)
    No COA finding linked to this contract.
    Not published

2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.

Tamper test: try changing this record

Demo

Edit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.

  1. 1. Record fingerprint changed
    stored   eada2c1f5b…5f23a1now      …
  2. 2. Block Merkle root changed
    stored   4a8c081022…24166cnow      …
  3. 3. Block #4472 hash changed
    stored   c3602b471a…d093c6now      …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.

Merkle proof (8 steps)

How this one record is tied to the block's Merkle root, without needing the other 233 records. Each step hashes the current value together with the sibling shown.

  1. leaf  eada2c1f5b1ab08637313724d1d82db66f5d96d31c9df62a695685a8b45f23a1
  2. 01 L eabc652b64c792c6d601aabf5fa94473899b095d050acf9dcdb95f555b2ff02c
  3. 02 R 6d931c1d29f1ff2110efa5899c44a677ffd5636784643d753591218d2cfd022b
  4. 03 R 955dd1f526cbbd6d50021766cd1eb093398b9c2d91bdf0d5b55a0009c7ea4ccd
  5. 04 L dd5721dd2f263de1518251643534a0b6af82e6831eb1a0db7a55e4e8491a192c
  6. 05 L 5cbd77214847abf899a5f181d3185f7d78b5505078c37ead9dae7814eba90d75
  7. 06 R 1ad2a7f6db84b17d544dd47526650ad30e6f08a57d0109a4ed5b79088cd7a0d3
  8. 07 L a98ccd7832dc7b51aed2dd6e04407c8161c5cd11b28ed3aed8e139353fbf1334
  9. 08 L cf1ff7c692623898c33eacf23bb4001bff9b8a5a4fed63f3689fd5c835fbcfde
  10. root  4a8c081022af0859d2473a5276d80074e21672b0d17bf7c9b6a82ae69924166c