Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LEYTE 5TH ED Award a ₱2.8M contract to AMB ENTERPRISESNational agencies
Transaction hash:
ebeb67b581f1a6e8d7df77a6453037041410b27fc08cb95ce6abebb162e14688
Status:
Included and unchanged
Block:
#3,328 2,685 blocks after it
Position in block:
Transaction 267 of 290
Award day:
Feb 8, 2018 (8 yrs 9 mo ago)
Value:
₱2,806,650.00
Project:
Construction/Improvement
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #3,328 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Regular Infra - GAA 2018 Other Infrastructure (CSSP)", i.e. the FY2018 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LEYTE 5TH ED awarded it to AMB ENTERPRISES on 2018-02-08.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 18IG0041: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2018-05-19). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored ebeb67b581…e14688now …
- 2. Block Merkle root changedstored feed48cc0a…4281c9now …
- 3. Block #3328 hash changedstored 48cf1c5092…971d6bnow …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (9 steps)
How this one record is tied to the block's Merkle root, without needing the other 289 records. Each step hashes the current value together with the sibling shown.
- leaf ebeb67b581f1a6e8d7df77a6453037041410b27fc08cb95ce6abebb162e14688
- 01 L eaee572c5fbdff8f6168eb0bf49405e78cefdfe96a8cc5357332c2f944f0764c
- 02 L 8a5c449959aed60d30ec87ce4d124eff50ca70970de21509e6c8e98784949f6a
- 03 R be4484ff0ee4c62d2b60daa303257bec12b963eace526e9606727b83c2da7644
- 04 L d4feae9347d4cc3099b1ede05a64c7e4f1e1bfd63829cfc2416482ff5ca36ab9
- 05 R 80b7f99f074cdc9f248d0abcbf019723119d2109c86f250f85fd69a11b333546
- 06 R d564ae7cbdc8f7481f86934d37ea51c910b90f6c22515f7ef2710243479e157a
- 07 R b1620398a545288a07ee60e8e1a20dc985e228e8744afc85c066be86d1c6c95e
- 08 R bfab8902a0a208007e82e51a0ce50f13955ccc50f703c849baef4f24b836a50c
- 09 L 69649e08db3b9260f3c5bc48bf5a5e155e55448fb08e0f71226428a8494c23f2
- root feed48cc0a5fa4c02b826d9a11e8907c6ecc00549491d21da9b8e469db4281c9