DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - EASTERN SAMAR DEO Award a ₱1.9M contract to TUBIGAN BUILDERSNational agencies
Transaction hash:
f740237d250f1350e76eebc32aca995c1ded96af4c111d7a702676a7aa27f93c
Status:
Included and unchanged
Block:
#2,728 3,285 blocks after it
Position in block:
Transaction 6 of 7
Award day:
May 3, 2016 (10 yrs 6 mo ago)
Value:
₱1,908,129.93
Project:
16IB0058 - Concreting of San Mateo – San Juan, FMR
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #2,728 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Outside Infra - GAA 2016 DA Farm-to-Market Roads", i.e. the FY2016 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - EASTERN SAMAR DEO awarded it to TUBIGAN BUILDERS on 2016-05-03.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 16IB0058: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2016-07-19). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored f740237d25…27f93cnow …
- 2. Block Merkle root changedstored 8bae715b3c…f816d7now …
- 3. Block #2728 hash changedstored 764c7a7286…972c20now …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (3 steps)
How this one record is tied to the block's Merkle root, without needing the other 6 records. Each step hashes the current value together with the sibling shown.
- leaf f740237d250f1350e76eebc32aca995c1ded96af4c111d7a702676a7aa27f93c
- 01 R f740237d250f1350e76eebc32aca995c1ded96af4c111d7a702676a7aa27f93c
- 02 L a6abe2d298d84d569c9163653690b58cc60068251e6f4ca098e9cb903445ae98
- 03 L 62dd3dbecafdb4d93ff370e438598e4e42ae6281ea822daff310704dead52d3f
- root 8bae715b3c3e3544f2eb097c61dd476dda1efb370b46d569bf0dad3422f816d7