Skip to content
FY2026 GAA: ₱6.79T
PisoScan
DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works

Transaction details

API
Transaction action

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - QUEZON 4TH ED Award a ₱11.5M contract to JEMAK CONSTRUCTION & SUPPLYNational agencies

Transaction hash:
fa6da133d7618e6379e44b1d7b4d51971477786b39d03cd131bc2ff10b5653c0
Status:
Included and unchanged
Block:
#4,506 1,507 blocks after it
Position in block:
Transaction 406 of 419
Award day:
Jul 13, 2021 (5 yrs 4 mo ago)

Accountability

Bill Sec. 3 and 19
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #4,506 signature valid Demo key, proves nothing about the governmentPublic key

Linked records: from budget to payment

Bill Sec. 5
  1. 1. Appropriation
    GAA line item · Sec. 5(b)
    DPWH lists the funding source as "Outside Infra - GAA 2021 DA FMR", i.e. the FY2021 GAA. The exact UACS line is not given.
    Partly
  2. 2. Allotment release
    SARO / allotment · Sec. 5(c)(iii)
    Not published per project. DBM releases SAROs, but not linked to individual contracts.
    Not published
  3. 3. Cash allocation
    Notice of Cash Allocation · Sec. 5(c)(iv)
    Not published per project.
    Not published
  4. 4. Contract award
    Notice of Award (PhilGEPS) · Sec. 5(d)
    DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - QUEZON 4TH ED awarded it to JEMAK CONSTRUCTION & SUPPLY on 2021-07-13.
    Found
  5. 5. Contract & progress
    Contract / progress report (DPWH) · Sec. 5(d)
    DPWH contract 21DL0140: Completed, 100% physical progress.
    Found
  6. 6. Payment
    Disbursement voucher · Sec. 5(c)(viii)
    Not published. No public source shows how much of this contract has been paid.
    Not published
  7. 7. Completion
    Certificate of completion · Sec. 5(d)
    DPWH marks the contract "Completed" (end 2021-12-30). The certificate itself is not published.
    Partly
  8. 8. Audit
    COA annual audit report · Sec. 5(e)(iii)
    No COA finding linked to this contract.
    Not published

2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.

Tamper test: try changing this record

Demo

Edit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.

  1. 1. Record fingerprint changed
    stored   fa6da133d7…5653c0now      …
  2. 2. Block Merkle root changed
    stored   0721b6020e…71eed0now      …
  3. 3. Block #4506 hash changed
    stored   5484aba143…e5e011now      …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.

Merkle proof (9 steps)

How this one record is tied to the block's Merkle root, without needing the other 418 records. Each step hashes the current value together with the sibling shown.

  1. leaf  fa6da133d7618e6379e44b1d7b4d51971477786b39d03cd131bc2ff10b5653c0
  2. 01 R fb80cca82fd5159989f80a4d89afd2a5ee4236e95df834d38e7d51faf503f2d7
  3. 02 L 6ad4797de3ce785f9fa21c406d5ee8a97704a850cbced2e9ad5a3b7d452ece57
  4. 03 L 6a94df5d5350dbf0cf1d0b8f098a140a6e370615dde978abe5306a20b734172b
  5. 04 R 73f47a6781f8c7724d35fcbc16225064d320a40d827cd775f3376f361f34b11b
  6. 05 L d7cdc80eb839001b25af4c90b7260496461e167447438cfbe020f9a8553fd6d2
  7. 06 R e8b25b3667a57c1131795e9033f64f94d3ce3a594cdbd7f18799d300e8aa14b6
  8. 07 R 2b544277feaacdd1f1357d6e214f0fc836392acfbdb024d7f32fc692550cd8a9
  9. 08 L 4b593eadc654138a96ab46ae00504dc299fb5558928383c62f6c428eba6c5f4c
  10. 09 L 1c1be720cd8e190ad93238f102c7a32cf4286090a757025ea09df202490048b8
  11. root  0721b6020e7ab9c359f3b4e015e8eee0bd6c576d0e97c4ac1cf0d1a49071eed0