DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAGAYAN 1ST DEO Award a ₱4.8M contract to PRIMITIVO P. ESLABON CONSTRUCTION & HARDWARENational agencies
Transaction hash:
fbe3440cd6ee103c444c75845fcb30443ff6d47ae05dd23b5a7d964bd1f22f9b
Status:
Included and unchanged
Block:
#3,987 2,026 blocks after it
Position in block:
Transaction 251 of 255
Award day:
Jan 6, 2020 (6 yrs 10 mo ago)
Value:
₱4,807,879.92
Project:
19BB0146 - Rehabilitation of Public Cemetery at Bu
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #3,987 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Outside Infra - GAA 2019 DILG Funds", i.e. the FY2019 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAGAYAN 1ST DEO awarded it to PRIMITIVO P. ESLABON CONSTRUCTION & HARDWARE on 2020-01-06.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 19BB0146: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2022-06-26). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored fbe3440cd6…f22f9bnow …
- 2. Block Merkle root changedstored 040a2b2900…1facf1now …
- 3. Block #3987 hash changedstored 89f05f69af…c4b9fdnow …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (8 steps)
How this one record is tied to the block's Merkle root, without needing the other 254 records. Each step hashes the current value together with the sibling shown.
- leaf fbe3440cd6ee103c444c75845fcb30443ff6d47ae05dd23b5a7d964bd1f22f9b
- 01 L fa73d06c2d686e26e93352b927a26827b0865564dfaf9756a9c5f6ff97a47422
- 02 L 6491fb09d95f634efdace15a6b080d5d30aaf287867a8491c81daadea7ff6c40
- 03 R dec78d22f43e50f70de6a8a1a6a5c52578e831f1acb70e9e940e74ee001c11f5
- 04 L df2e3350b839ac0bb4777e30b71899fa06e3573bc1629dc75d755856a63af920
- 05 L f2d144c0e5993af69d1481090354e7366412007f3d0dd216e28bfb164923eeb6
- 06 L 5777b09f8099e45175c24b3c18ed512803265ea04f96ea8c21d5e88fdc47e325
- 07 L 7d9388652abd506284dfea3bfe554224abecf259e30a92baeed924b7cbb35503
- 08 L 6cbbb82b9a870308c87a5f5c3d350af4be64013d9264792a752250bac90ef34b
- root 040a2b2900bed3dc95514bbc1f8c0117e50f13e41bdab3df81a955707a1facf1