Contract awards located here
398
₱767.8M listed value · PhilGEPS
DPWH contracts located here
80
₱1.50B contract value
COA audit opinion
qualifiedCY2024
COA executive summary 80 DPWH contracts
| Contract ID | Start | Description | Status | Office | Contractor | Amount |
|---|---|---|---|---|---|---|
| 20AI0009 | 6 yrs 9 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY.SAN PEDRO ILI, ALCALA, PANGASINANBuildings and Facilities | Completed | Pangasinan 3rd DEO | RPPARAYNO CONSTRUCTION | ₱5.8M |
| 20AI0013 | 6 yrs 9 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. ATAINAN, ALCALA, PANGASINANBuildings and Facilities | Completed | Pangasinan 3rd DEO | RPPARAYNO CONSTRUCTION | ₱1.9M |
| 20AI0029 | 6 yrs 9 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGNO RIVER, BRGY. LAOAC (LEFT BANK), ALCALA, PANGASINANFlood Control and Drainage | Completed | Pangasinan 3rd DEO | AMP 723 CONSTRUCTION CORPORATION (FORMERLY: A.M.P. CONSTRUCTION) | ₱37.2M |
| 19AI0316 | 7 yrs 2 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN PEDRO ILI, ALCALA, PANGASINANBuildings and Facilities | Completed | Pangasinan 3rd DEO | BET CONSTRUCTION & SUPPLY | ₱4.8M |
| 19AJ0099 | 7 yrs 3 mo ago | CONSTRUCTION (COMPLETION) OF WAIG-TOBOR BRIDGE AND APPROACHES, BARANGAY WAIG, MALASIQUI, PANGASINANBridges | Completed | Pangasinan 4th DEO | JEUSMACK BUILDERS & CONSTRUCTION SUPPLY | ₱19.1M |
| 19AI0261 | 7 yrs 4 mo ago | CONCRETING OF ROAD, BARANGAY POGO-BARANGAY DIAZ, BAUTISTA, PANGASINANRoads | Completed | Pangasinan 3rd DEO | MIGHTYWAY CONSTRUCTION AND SUPPLY | ₱14.1M |
| 19AI0114 | 7 yrs 5 mo ago | CONSTRUCTION OF ARTACHO MULTI-PURPOSE BUILDING (COVERED COURT), ARTACHO, BAUTISTA, PANGASINANBuildings and Facilities | Completed | Pangasinan 3rd DEO | W.M. SALAYOG CONSTRUCTION & GEN MERCHADISE | ₱1.9M |
| 18AI0353 | 7 yrs 11 mo ago | CONSTRUCTION OF THREE STOREY SIX CLASSROOM SCHOOL BUILDING LAOAC E/S, ALCALA, PANGASINANBuildings and Facilities | Completed | Pangasinan 3rd DEO | JBERNARDO CONSTRUCTION AND SUPPLY | ₱17.9M |
| 18AI0305 | 8 yrs 1 mo ago | CONSTRUCTION OF RHU, ALCALA RHU II, ALCALA, PANGASINANBuildings and Facilities | Completed | Pangasinan 3rd DEO | W.M. SALAYOG CONSTRUCTION & GEN MERCHADISE | ₱10.5M |
| 18AI0269 | 8 yrs 3 mo ago | CONSTRUCTION OF BHS, ARTACHO BHS, BAUTISTA, PANGASINANBuildings and Facilities | Completed | Pangasinan 3rd DEO | MIGHTYWAY CONSTRUCTION AND SUPPLY | ₱1.2M |
| 18AI0268 | 8 yrs 3 mo ago | CONCRETING OF ITORMA CABICALAN, BRGY. KISIKIS FMR, BRGY. KISIKIS, ALCALA, PANGASINANRoads | Completed | Pangasinan 3rd DEO | MCB CONSTRUCTION & SUPPLY | ₱4.7M |
| 18AI0265 | 8 yrs 4 mo ago | CONCRETING OF LAOAC FMR, BRGY. LAOAC, ALCALA, PANGASINANRoads | Completed | Pangasinan 3rd DEO | MIGHTYWAY CONSTRUCTION AND SUPPLY | ₱7.0M |
| 18AI0101 | 8 yrs 7 mo ago | CONSTRUCTION OF BRGY. HALL, BRGY. SAN JUAN, ALCALA, PANGASINANBuildings and Facilities | Completed | Pangasinan 3rd DEO | W.M. SALAYOG CONSTRUCTION & GEN MERCHADISE | ₱977.5K |
| 18AI0039 | 8 yrs 7 mo ago | REHAB OF DIKE W/ PROTECTION WORKS ALONG AGNO RIVER BASIN AND ALLIED RIVERS FLOOD CTRL PROJ - BRGY. KFlood Control and Drainage | Completed | Pangasinan 3rd DEO | EGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) | ₱18.8M |
| 18AI0044 | 8 yrs 7 mo ago | AGNO RIVER BASIN AND ALLIED RIVERS FLOOD CONTROL PROJECT - IMPROVEMENT OF VILLASIS-ALCALA EARTHDIKE,Flood Control and Drainage | Completed | Pangasinan 3rd DEO | EGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) | ₱18.6M |
| 18AI0037 | 8 yrs 7 mo ago | REHAB OF DIKE W/ PROTECTION WORKS ALONG AGNO RIVER BASIN AND ALLIED RIVERS FLOOD CTRL PROJ, BRGY. SAFlood Control and Drainage | Completed | Pangasinan 3rd DEO | EGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) | ₱18.8M |
| 18AI0102 | 8 yrs 8 mo ago | CONSTN OF BARANGAY HALL, BRGY. SAN PEDRO ILI, ALCALA, PANGASINANBuildings and Facilities | Completed | Pangasinan 3rd DEO | AQUINO-DELA CRUZ ENGINEERING AND CONSTRUCTION | ₱973.6K |
| 18AI0103 | 8 yrs 8 mo ago | CONSTN OF DAY CARE CENTER BLDG AT BRGY. POBLACION WEST, ALCALA, PANGASINANBuildings and Facilities | Completed | Pangasinan 3rd DEO | 2-R CONSTRUCTION & SUPPLY | ₱970.6K |
| 18AI0105 | 8 yrs 8 mo ago | CONSTN OF PINDANGAN EAST SR CITIZEN BLDG, BRGY. PINDANGAN EAST, ALCALA, PANGASINANBuildings and Facilities | Completed | Pangasinan 3rd DEO | 2-R CONSTRUCTION & SUPPLY | ₱974.0K |
| 18AI0107 | 8 yrs 8 mo ago | CONCRETING OF DELOS SANTOS ST. EXT ROAD, BRGY. SAN NICOLAS, ALCALA, PANGASINANRoads | Completed | Pangasinan 3rd DEO | 2-R CONSTRUCTION & SUPPLY | ₱2.8M |
| 18AI0112 | 8 yrs 8 mo ago | CONCRETING OF ROADS, SITIO PRIMICIAS, BRGY. BERSAMIN, ALCALA, PANGASINANRoads | Completed | Pangasinan 3rd DEO | MCB CONSTRUCTION & SUPPLY | ₱2.3M |
| 18AJ0037 | 8 yrs 8 mo ago | CONSTRUCTION OF PROTECTION WORKS ALONG AGNO RIVER, ATAYNAN SECTION, BAYAMBANG, PANGASINANFlood Control and Drainage | Completed | Pangasinan 4th DEO | KENWOOD CONSTRUCTION ENTERPRISES CORPORATION (FORMERLY:KENWOOD CONSTRUCTION ENTERPRISES) | ₱29.4M |
| 18AI0084 | 8 yrs 9 mo ago | AGNO RIVER BASIN AND ALLIED RIVERS FLOOD CTRL PROJ-CONST'N OF BANK PROTECTIO, BRGY. POGO-DIAZ, BAUTIFlood Control and Drainage | Completed | Pangasinan 3rd DEO | BET CONSTRUCTION & SUPPLY | ₱18.7M |
| 17Z00003 | 9 yrs 3 mo ago | AGNO RIVER BASIN FLOOD CONTROL PROJECT (PHASE1)-CONSTRUCTION OF PROTECTION WORKS USING GABIONS AND MATTRESSES. BRGY. DORONGAN SAWAT, STA. 2+840 TO STA.3+140 AND STA. 3+140 T0 STA. 3+640, DORONGAN KETAKET, STA 1+592 TO STA. 2+840 MANGATAREM; (PHASE II-A)-RGAA 2017 MFO-2 | On-Going | Flood Control Management Cluster | MSB VITUG CONSTRUCTION INC. (FORMERLY MSB VITUG CONSTRUCTION) | ₱363.2M |
| 17AI0108 | 9 yrs 5 mo ago | CONSTN OF TWO UNITS MPB (DAY CARE & HEALTH CENTER) AT BRGY. MACAYO, ALCALA, PANGANSINANBuildings and Facilities | Completed | Pangasinan 3rd DEO | BET CONSTRUCTION & SUPPLY | ₱1.9M |
Records are placed by the location the source gives. Some national-level awards and DPWH contracts have no location and are not counted here.