| afa602650ef5… | tala2013-001 | 13 yrs 1 mo ago | 2X2X12 F.L. | BARANGAY TALA, ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱750 |
| a21af0dc8e2b… | tala2013-001 | 13 yrs 1 mo ago | ASSTED NAIL | BARANGAY TALA, ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱95 |
| 385e91e7efa7… | — | 13 yrs 2 mo ago | PORTLAND CEMENT | MUNICIPALITY OF ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱52.0K |
| edc3b25b213b… | — | 13 yrs 2 mo ago | LABORERS 10/days | MUNICIPALITY OF ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱30.0K |
| 7b33da4bcf86… | — | 13 yrs 2 mo ago | GRAVEL | MUNICIPALITY OF ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱25.0K |
| 95ac746926b7… | — | 13 yrs 2 mo ago | SELECTED BARROW | MUNICIPALITY OF ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱11.9K |
| 47287375798d… | — | 13 yrs 2 mo ago | WASHED SAND | MUNICIPALITY OF ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱8.6K |
| fa6ae8c617ad… | — | 13 yrs 2 mo ago | SKILLED LABORERS 89days | MUNICIPALITY OF ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱6.3K |
| ec66dc34e5a2… | — | 13 yrs 2 mo ago | 4 CHB | MUNICIPALITY OF ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱6.0K |
| eeb23c0a7f23… | — | 13 yrs 2 mo ago | FOREMAN 10days | MUNICIPALITY OF ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱4.5K |
| 9e98bc3d192c… | — | 13 yrs 2 mo ago | 10 MM DEF BAR | MUNICIPALITY OF ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱2.9K |
| 93d52a38e9ff… | — | 13 yrs 2 mo ago | BILLBOARD | MUNICIPALITY OF ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱1.0K |
| 566858d6338c… | — | 13 yrs 2 mo ago | PLASTIC PAIL | MUNICIPALITY OF ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱600 |
| c220bad94f0f… | — | 13 yrs 2 mo ago | 16 TIE WIRE | MUNICIPALITY OF ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱150 |
| 17d5068a40e7… | — | 13 yrs 2 mo ago | ASSORTED NAIL | MUNICIPALITY OF ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱75 |
| 958ca821d276… | tapulao2013-011 | 13 yrs 2 mo ago | PORTLAND CEMENT | BARANGAY TAPULAO, ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱18.4K |
| c2bd95b2b3f8… | tapulao2013-011 | 13 yrs 2 mo ago | LABORERS 5 DAYS | BARANGAY TAPULAO, ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱10.0K |
| 0489be6129a4… | tapulao2013-011 | 13 yrs 2 mo ago | GRAVEL | BARANGAY TAPULAO, ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱5.8K |
| 99cf4281ce85… | tapulao2013-011 | 13 yrs 2 mo ago | SELECTED BARROW | BARANGAY TAPULAO, ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱4.1K |
| 4c4ce2e3cbea… | tapulao2013-011 | 13 yrs 2 mo ago | SKILLED LABORERS 5 DAYS | BARANGAY TAPULAO, ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱3.5K |
| 1979c81fbaa8… | tapulao2013-011 | 13 yrs 2 mo ago | WASHED SAND | BARANGAY TAPULAO, ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱3.3K |
| ce2a597df520… | tapulao2013-011 | 13 yrs 2 mo ago | FOREMAN 5 DAYS | BARANGAY TAPULAO, ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱2.3K |
| 4fe11a5ee8da… | tapulao2013-011 | 13 yrs 2 mo ago | CONCRETE MIXER 3 DAYS | BARANGAY TAPULAO, ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱2.1K |
| c624a7e3404c… | tapulao2013-011 | 13 yrs 2 mo ago | 10 MM DEF BAR | BARANGAY TAPULAO, ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱2.1K |
| ced19d4f2fe0… | tapulao2013-011 | 13 yrs 2 mo ago | 4 THICK CHB | BARANGAY TAPULAO, ORANI, BATAAN | ORANI BUILDERS SUPPLY | ₱2.0K |