Castillejos
Region III (Central Luzon) ›Zambales › City / municipality · PSGC 0307104000
Contract awards located here
45
₱85.3M listed value · PhilGEPS
DPWH contracts located here
152
₱4.95B contract value
COA audit opinion
152 DPWH contracts
| Contract ID | Start | Description | Status | Office | Contractor | Amount |
|---|---|---|---|---|---|---|
| 23CM0017 | 3 yrs 9 mo ago | CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, REHABILITATION OF PAMATAWAN RIVER UPSTREAM (KANAYNAYAN SECTION), CASTILLEJOS, ZAMBALESFlood Control and Drainage | Completed | Zambales 2nd DEO | ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) | ₱49.2M |
| 23CM0024 | 3 yrs 9 mo ago | FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, REHABILITATION OF PAMATAWAN RIVER DOWNSTREAM (OLD SAN AGUSTIN SECTION), CASTILLEJOS, ZAMBALESFlood Control and Drainage | Completed | Zambales 2nd DEO | ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) | ₱96.5M |
| 23CM0004 | 3 yrs 9 mo ago | REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS OLONGAPO - BUGALLON ROAD (OBR), K0145+866 - K0146+180, K0146+942 - K0147+300, K0149+556 - K0149+818.75, CASTILLEJOS, ZAMBALESGAA 2023 OO-1 | On-Going | Zambales 2nd DEO | M.V.GUBALLA CONSTRUCTION CORPORATION (FORMERLY: M.V. GUBALLA CONSTRUCTION) | ₱19.6M |
| 23CM0011 | 3 yrs 9 mo ago | NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS CAWAG-PHILSECO BYPASS ROAD - PACKAGE 5, ZAMBALESRoads | Completed | Zambales 2nd DEO | HIGH STRENGTH DEV. CORPORATION | ₱49.0M |
| 21CM0060 | 4 yrs 2 mo ago | CONSTRUCTION OF CONCRETE ROAD AT DOLITAN LAND SHELTER, BARANGAY NAGBUNGA, SAN MARCELINO, ZAMBALESRoads | Completed | Zambales 2nd DEO | JAMJET CONSTRUCTION SERVICES | ₱9.9M |
| 21CM0059 | 4 yrs 2 mo ago | CONCRETING AND IMPROVEMENT OF CAMIRING ROAD, BARANGAY CONSUELO NORTE, SAN MARCELINO, ZAMBALESRoads | Completed | Zambales 2nd DEO | RAIK CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: RAIK CONSTRUCTION AND SUPPLY) | ₱4.8M |
| 22CM0061 | 4 yrs 7 mo ago | FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, REHABILITATION OF FLOOD MITIGATION AND DRAINAGE SYSTEM OF PAMATAWAN RIVER (LOOC SECTION), STA. 18+690 - STA. 19+090, CASTIFlood Control and Drainage | Completed | Zambales 2nd DEO | STO. CRISTO CONSTRUCTION & TRADING INC. (FOR: STO. CRISTO CONSTRUCTION & TRADING) | ₱77.2M |
| 22CM0062 | 4 yrs 7 mo ago | CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, REHABILITATION OF FLOOD MITIGATION AND DRAINAGE SYSTEM OF PAMATAWAN RIVER (SAN AGUSTIN SECTION), STA. 21+974 - STA. 22+374, CASTILLEJOS, ZAMBALESFlood Control and Drainage | Completed | Zambales 2nd DEO | STO. CRISTO CONSTRUCTION & TRADING INC. (FOR: STO. CRISTO CONSTRUCTION & TRADING) | ₱77.2M |
| 22CM0063 | 4 yrs 7 mo ago | CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, REHABILITATION OF FLOOD MITIGATION AND DRAINAGE SYSTEM OF CAMACHILE RIVER (UPSTREAM), STA. 19+964 - STA. 20+129, CASTILLEJOS, ZAMBALESFlood Control and Drainage | Completed | Zambales 2nd DEO | ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) | ₱77.2M |
| 22CM0064 | 4 yrs 7 mo ago | CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, REHABILITATION OF FLOOD MITIGATION AND DRAINAGE SYSTEM OF CAMACHILE RIVER (UPSTREAM), STA. 19+764 - STA. 19+964, CASTILLEJOS, ZAMBALESFlood Control and Drainage | Completed | Zambales 2nd DEO | ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) | ₱77.2M |
| 22CM0065 | 4 yrs 7 mo ago | CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, REHABILITATION OF FLOOD MITIGATION AND DRAINAGE SYSTEM OF CAMACHILE RIVER (UPSTREAM), STA. 21+960 - STA. 22+128, CASTILLEJOS, ZAMBALESFlood Control and Drainage | Completed | Zambales 2nd DEO | ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) | ₱77.2M |
| 22CM0015 | 4 yrs 8 mo ago | NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CAWAG-PHILSECO BYPASS ROAD-PACKAGE 2, ZAMBALESRoads | Completed | Zambales 2nd DEO | HIGH STRENGTH DEV. CORPORATION | ₱52.7M |
| 22CM0021 | 4 yrs 8 mo ago | FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, REHABILITATION OF PAMATAWAN RIVER, STA. 30+540 - STA. 30+935, BRGY. DEL PILAR, CASTILLEJOS, ZAMBALESFlood Control and Drainage | Completed | Zambales 2nd DEO | REPOLMAN CONSTRUCTION CORP. (FORMERLY: REPOLMAN CONSTRUCTION) | ₱67.5M |
| 22CM0019 | 4 yrs 8 mo ago | FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, REHABILITATION OF PAMATAWAN RIVER (ALINDAYAT SECTION), STA. 22+374 - STA. 22+844, BRGY. SAN AGUSTIN, CASTILLEJOS, ZAMBALESFlood Control and Drainage | Completed | Zambales 2nd DEO | ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) | ₱82.0M |
| 22CM0020 | 4 yrs 8 mo ago | FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, REHABILITATION OF PAMATAWAN RIVER (CABALLUCAN SECTION), STA. 30+935 - STA. 31+419, BRGY. SAN PABLO, CASTILLEJOS, ZAMBALESFlood Control and Drainage | Completed | Zambales 2nd DEO | ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) | ₱82.0M |
| 22CM0046 | 4 yrs 9 mo ago | CONSTRUCTION OF ROAD AT PUROK 4, BARANGAY DEL PILAR, CASTILLEJOS, ZAMBALESRoads | Completed | Zambales 2nd DEO | R.D. FLORES CONSTRUCTION | ₱5.4M |
| 22CM0047 | 4 yrs 9 mo ago | CONSTRUCTION OF ROAD AT SITIO SAN ISIDRO - SITIO BAGONG SILANG, BARANGAY SAN PABLO, CASTILLEJOS, ZAMBALESRoads | Completed | Zambales 2nd DEO | RGZAMORA CONSTRUCTION AND TRADING | ₱4.9M |
| 22CM0051 | 4 yrs 9 mo ago | CONSTRUCTION OF SANG-ATAN BRIDGE (BOX-CULVERT), BARANGAY SAN PABLO, CASTILLEJOS, ZAMBALESBridges | Completed | Zambales 2nd DEO | RGZAMORA CONSTRUCTION AND TRADING | ₱5.3M |
| 22CM0031 | 4 yrs 9 mo ago | ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES, CONSTRUCTION OF ROAD AT PASCUAL ST. BARANGAY MAGSAYSAY, CASTILLEJOS, ZAMBALESRoads | Completed | Zambales 2nd DEO | RGZAMORA CONSTRUCTION AND TRADING | ₱5.9M |
| 22CM0032 | 4 yrs 9 mo ago | ACCESS ROAD AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES, CONSTRUCTION OF ROAD AT PUROK 1, BARANGAY DEL PILAR, CASTILLEJOS, ZAMBALESRoads | Completed | Zambales 2nd DEO | RGZAMORA CONSTRUCTION AND TRADING | ₱4.8M |
| 22CM0033 | 4 yrs 9 mo ago | ACCESS ROAD AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES, CONSTRUCTION OF ROAD AT SITIO ABOT, BARANGAY CAWAG, SUBIC, ZAMBALESRoads | Completed | Zambales 2nd DEO | REPOLMAN CONSTRUCTION CORP. (FORMERLY: REPOLMAN CONSTRUCTION) | ₱4.8M |
| 22CM0034 | 4 yrs 9 mo ago | ACCESS ROAD AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES, CONSTRUCTION OF ROAD AT SITIO ALUSIIS - NAGBAYAN ROAD, CASTILLEJOS, ZAMBALESRoads | Completed | Zambales 2nd DEO | RGZAMORA CONSTRUCTION AND TRADING | ₱4.9M |
| 22CM0016 | 4 yrs 9 mo ago | NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CAWAG-PHILSECO BYPASS ROAD-PACKAGE 3, ZAMBALESRoads | Completed | Zambales 2nd DEO | HIGH STRENGTH DEV. CORPORATION | ₱81.4M |
| 22CM0029 | 4 yrs 9 mo ago | ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES, CONSTRUCTION OF ROAD AT BARANGAY SAN JOSE - BARANGAY SAN PABLO, CASTILLEJOS, ZAMBALESRoads | Completed | Zambales 2nd DEO | RGZAMORA CONSTRUCTION AND TRADING | ₱6.9M |
| 21CM0076 | 5 yrs 2 mo ago | CONSTRUCTION OF CLASSROOMS, 2-STOREY, 6-CLASSROOM SCHOOL BUILDING SITIO BARING, SAN NICOLAS, CASTILLEJOS, ZAMBALESBuildings and Facilities | Completed | Zambales 2nd DEO | JAM-C BUILDERS | ₱29.4M |
Records are placed by the location the source gives. Some national-level awards and DPWH contracts have no location and are not counted here.