Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Santa Cruz

Region III (Central Luzon) ›Zambales › City / municipality · PSGC 0307113000

Contract awards located here

1,298
₱4.85B listed value · PhilGEPS

DPWH contracts located here

128
₱4.51B contract value

COA audit opinion

unmodifiedCY2024
44 of 84 prior-year audit recommendations fully implemented
COA executive summary
1,298 awards
Record IDReferenceAgeProject titleProcuring entityAwarded toAmount
aee5313e3010…2021-724 yrs 11 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION/REHABILITATION OF BOX CULVERT IN PUROK 2, BARANGAY SABANG, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱803.8K
fbfc68da04ea…2021-724 yrs 11 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION/REHABILITATION OF BOX CULVERT IN PUROK 2, BARANGAY SABANG, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱803.8K
ce212f493b52…2021-724 yrs 11 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION/REHABILITATION OF BOX CULVERT IN PUROK 2, BARANGAY SABANG, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱803.8K
15d8b050c928…2021-724 yrs 11 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION/REHABILITATION OF BOX CULVERT IN PUROK 2, BARANGAY SABANG, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱803.8K
8e9b3db18ea1…2021-724 yrs 11 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION/REHABILITATION OF BOX CULVERT IN PUROK 2, BARANGAY SABANG, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱803.8K
8ae08156680b…2021-724 yrs 11 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION/REHABILITATION OF BOX CULVERT IN PUROK 2, BARANGAY SABANG, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱803.8K
825cdcfb189b…2021-724 yrs 11 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION/REHABILITATION OF BOX CULVERT IN PUROK 2, BARANGAY SABANG, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱803.8K
734d73ce1da1…2021-714 yrs 11 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF BOX CULVERT AT BARANGAY TUBO-TUBO SOUTH, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱598.0K
a18b11a017b7…2021-714 yrs 11 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF BOX CULVERT AT BARANGAY TUBO-TUBO SOUTH, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱598.0K
70aba629fa2e…2021-714 yrs 11 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF BOX CULVERT AT BARANGAY TUBO-TUBO SOUTH, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱598.0K
ede896e53ded…2021-714 yrs 11 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF BOX CULVERT AT BARANGAY TUBO-TUBO SOUTH, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱598.0K
e89398f379ad…2021-714 yrs 11 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF BOX CULVERT AT BARANGAY TUBO-TUBO SOUTH, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱598.0K
6b5b1154d096…2021-714 yrs 11 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF BOX CULVERT AT BARANGAY TUBO-TUBO SOUTH, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱598.0K
dec7060a3923…2021-714 yrs 11 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF BOX CULVERT AT BARANGAY TUBO-TUBO SOUTH, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱598.0K
bfd2034a9330…2021-714 yrs 11 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF BOX CULVERT AT BARANGAY TUBO-TUBO SOUTH, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱598.0K
ea900ddf0615…2021-714 yrs 11 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF BOX CULVERT AT BARANGAY TUBO-TUBO SOUTH, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱598.0K
c350443f8757…2021-015 yrs agoINVITATION TO BID FOR THE CONSTRUCTION OF MULTI-PURPOSE HALL, SITIO ACOJE, BARANGAY LUCAPON SOUTH, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱1.5M
7faf4aee08db…2021-015 yrs 1 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF DRAINAGE CANAL PHASE 2, PUROK 3, BARANGAY LIPAY, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALESTHREE CM BUILDERS₱1.2M
4eb9514263d8…2021-625 yrs 1 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF BUILDING FOR THE SOLID WASTE PROCESSING TECHNOLOGY FACILITY/EQUIPMENT (PHASE I) AT BRGY. SABANG, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALES1C4M BUILDERS INC₱4.2M
31c86929463c…2021-625 yrs 1 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF BUILDING FOR THE SOLID WASTE PROCESSING TECHNOLOGY FACILITY/EQUIPMENT (PHASE I) AT BRGY. SABANG, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALES1C4M BUILDERS INC₱4.2M
c74d8077610f…2021-625 yrs 1 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF BUILDING FOR THE SOLID WASTE PROCESSING TECHNOLOGY FACILITY/EQUIPMENT (PHASE I) AT BRGY. SABANG, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALES1C4M BUILDERS INC₱4.2M
a92776a4b883…2021-625 yrs 1 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF BUILDING FOR THE SOLID WASTE PROCESSING TECHNOLOGY FACILITY/EQUIPMENT (PHASE I) AT BRGY. SABANG, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALES1C4M BUILDERS INC₱4.2M
83bcba0d4e20…2021-625 yrs 1 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF BUILDING FOR THE SOLID WASTE PROCESSING TECHNOLOGY FACILITY/EQUIPMENT (PHASE I) AT BRGY. SABANG, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALES1C4M BUILDERS INC₱4.2M
8d6efb2d2e5a…2021-625 yrs 1 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF BUILDING FOR THE SOLID WASTE PROCESSING TECHNOLOGY FACILITY/EQUIPMENT (PHASE I) AT BRGY. SABANG, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALES1C4M BUILDERS INC₱4.2M
b1a03e82f361…2021-625 yrs 1 mo agoINVITATION TO BID FOR THE PROJECT CONSTRUCTION OF BUILDING FOR THE SOLID WASTE PROCESSING TECHNOLOGY FACILITY/EQUIPMENT (PHASE I) AT BRGY. SABANG, STA. CRUZ, ZAMBALESMUNICIPALITY OF STA. CRUZ, ZAMBALES1C4M BUILDERS INC₱4.2M

Records are placed by the location the source gives. Some national-level awards and DPWH contracts have no location and are not counted here.