San Jose
Region V (Bicol Region) ›Camarines Sur › City / municipality · PSGC 0501733000
Contract awards located here
164
₱392.6M listed value · PhilGEPS
DPWH contracts located here
99
₱2.50B contract value
COA audit opinion
99 DPWH contracts
| Contract ID | Start | Description | Status | Office | Contractor | Amount |
|---|---|---|---|---|---|---|
| 22FG0065 | 4 yrs 7 mo ago | CONSTRUCTION OF ROAD SECTION 1: STA.0+000.00-STA. 0+135.80 SECTION 2: STA.0+000.00-STA.0+086.50, SECTION 3: STA. 0+000.00-STA.0+074.00,SECTION 4: STA0+520.00-STA.0+741.00,ZONE 3,BARANGAY PALALE,SAN JOSE, CAMARINES SURRoads | Completed | Camarines Sur 4th DEO | SMDP CONSTRUCTION | ₱4.7M |
| 22FG0067 | 4 yrs 7 mo ago | CONSTRUCTION OF ROAD SECTION 1: STA.0+000.00-STA.0+125.30, SECTION 2: STA.0+000.00-STA.0+100.30 SECTION 3: STA.0+000.00-STA.0+97.20, SECTION 4 STA.0+000.00-STA.0+277.00, ZONE 3, BARANGAY TOMINAWOG, SAN JOSE CAMARINES SURRoads | Completed | Camarines Sur 4th DEO | SMDP CONSTRUCTION | ₱4.7M |
| 22FG0053 | 4 yrs 7 mo ago | CONSTRUCTION OF ACCESS ROAD, SAN JOSE, CAMARINES SURRoads | Completed | Camarines Sur 4th DEO | IA FERRER CONSTRUCTION & SUPPLY | ₱8.1M |
| 22FG0033 | 4 yrs 8 mo ago | CONSTRUCTION OF BY-PASS/DIVERSION ROAD ALONG JCT. NATO - SABANG COASTAL ROAD, CALALAHAN SECTIONSTA.4+511.00 - STA.4+983.00SAN JOSE, CAMARINES SURRoads | Completed | Camarines Sur 4th DEO | ALRO CONSTRUCTION & DEVELOPMENT CORP. | ₱72.4M |
| 22FG0044 | 4 yrs 8 mo ago | CONSTRUCTION OF ROAD SECTION 1: STA. 0+000-STA. 0+400.00, SECTION 2: STA. 0+000-STA. 0+002.75, SECTION 3: STA. 0+080.30-STA. 0+260.00, SECTION 4: STA. 0+000.00-STA. 0+100.00, ZONE 4, BARANGAY CALALAHAN, SAN JOSE, CAMARINES SURRoads | Completed | Camarines Sur 4th DEO | SMDP CONSTRUCTION | ₱4.7M |
| 22FG0045 | 4 yrs 8 mo ago | CONSTRUCTION OF ROAD, SECTION 1: STA. 0+000.00-STA. 0+570.00 (R/S), SECTION 2: STA. 0+000.00-STA. 0+131.00 (B/S), SITIO BAHOG, BARANGAY CALALAHAN, SAN JOSE, CAMARINES SURRoads | Completed | Camarines Sur 4th DEO | SMDP CONSTRUCTION | ₱4.7M |
| 22FG0031 | 4 yrs 8 mo ago | CONSTRUCTION OF ROAD, SITIO CATAN-AGAN, BARANGAY SALOGON TO BARANGAY PONGLONSECTION 1: STA.0+000.00 - STA.0+078.00SECTION 2: STA.0+446.00 - STA.0+824.20SECTION 3: STA.0+910.70 - STA.1+696.00SAN JOSE, CAMARINES SURRoads | Completed | Camarines Sur 4th DEO | SMDP CONSTRUCTION | ₱4.7M |
| 22FG0014 | 4 yrs 9 mo ago | REHABILITATION / MAJOR REPAIR OF PERMANENT BRIDGE, RANGAS BRIDGE II (B02550LZ) ALONG SAN RAFAEL-MAMPIRAO-SAN JOSE ROAD, BARANGAY MAMPIRAO, SAN JOSE, CAMARINES SURBridges: Rehabilitation - Concrete (Superstructure) - without Piles, Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry) | Completed | Camarines Sur 4th DEO | E.A. SANCHO CONST. INC. (FORM. E.A. SANCHO CONST.) | ₱4.6M |
| 22FG0015 | 4 yrs 9 mo ago | CONSTRUCTION OF BY PASS AND DIVERSION ROAD, JCT. NATO - SABANG COASTAL ROAD (TAGAS BRIDGE 2) CAMARINES SURBridges: Construction - Concrete (Superstructure) - with Driven Piles, Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry) | Completed | Camarines Sur 4th DEO | E.A. SANCHO CONST. INC. (FORM. E.A. SANCHO CONST.) | ₱49.0M |
| 21FG0065 | 5 yrs ago | CONSTRUCTION OF BY-PASS AND DIVERSION ROAD, JUNCTION NATO - SABANG COASTAL ROAD, TAGAS SECTION PHASE-II, CAMARINES SURSECTION 1: STA.3+550.00 - STA.3+590.00SECTION 2: STA.3+685.00 - STA.4+210.00TAGAS, SAN JOSE, CAMARINES SURBridges: Construction - Concrete (Superstructure) - with Driven Piles, Roads: Construction - PCCP | Completed | Camarines Sur 4th DEO | ALRO CONSTRUCTION & DEVELOPMENT CORP. | ₱91.7M |
| 21FG0052 | 5 yrs 2 mo ago | CONSTRUCTION OF BYPASS AND DIVERSION ROADJCT. NATO - SABANG COASTAL ROAD (CASUNA BRIDGE), CAMARINES SURSTA.0+930.00 - STA.2+150.00STA.3+218.60 - STA.3+460.00TIGAON AND SAN JOSE, CAMARINES SURBridges: Construction - Concrete (Superstructure) - with Driven Piles, Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - PCCP | Completed | Camarines Sur 4th DEO | ALRO CONSTRUCTION & DEVELOPMENT CORP. | ₱96.5M |
| 21FG0060 | 5 yrs 2 mo ago | CONSTRUCTION OF BY-PASS AND DIVDERSION ROAD, JCT. NATO - SABANG COASTAL ROAD, TAGAS SECTIONSECTION 1: STA.3+460.00 - STA.3+550.00SECTION 2: STA.3+590.00 - STA.3+685.00TAGAS, SAN JOSE, CAMARINES SURBridges: Rehabilitation - Concrete (Superstructure) - without Piles, Roads: Construction - PCCP | Completed | Camarines Sur 4th DEO | ALRO CONSTRUCTION & DEVELOPMENT CORP. | ₱23.5M |
| 21FG0089 | 5 yrs 6 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING,PALALE, SAN JOSE, CAMARINES SURBuildings and Facilities | Completed | Camarines Sur 4th DEO | MRBAY CONSTRUCTION | ₱1000.0K |
| 21FG0096 | 5 yrs 6 mo ago | REHABILITATION OF MULTI-PURPOSE BUILDINGTAGAS/SOLEDAD, SAN JOSE, CAMARINES SURBuildings and Facilities | Completed | Camarines Sur 4th DEO | HRB CONSTRUCTION | ₱1.9M |
| 21FG0072 | 5 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING,TEROGO, CARAMOAN, CAMARINES SURBuildings and Facilities | Completed | Camarines Sur 4th DEO | MRBAY CONSTRUCTION | ₱940.3K |
| 21FG0048 | 5 yrs 8 mo ago | CONSTRUCTION OF ROAD, CALALAHAN/SAN JUAN/DOLO, CALALAHAN/SAN JUAN/DOLO, SAN JOSE, CAMARINES SURRoads | Completed | Camarines Sur 4th DEO | LIMCORE CONSTRUCTION AND SUPPLY | ₱2.8M |
| 20FG0090 | 5 yrs 11 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (LIVELIHOOD CENTER)Buildings and Facilities | Completed | Camarines Sur 4th DEO | HRB CONSTRUCTION | ₱24.7M |
| 20FG0076 | 6 yrs ago | CONSTRUCTION/IMPROVEMENT OF LOCAL ROADS 1) BRGY. VINAGRE: STA.0+000.00 - STA.0+150.00 2) BRGY. DEL CARMEN: STA.0+000.00 - STA.0+076.00 BRGY. VINAGRE, TIGAON/BRGY. DEL CARMEN, SAN JOSE, CAMARINES SURRoads | Completed | Camarines Sur 4th DEO | JO20 CONSTRUCTION AND SUPPLY | ₱1.9M |
| 20FG0081 | 6 yrs ago | ROAD CONSTRUCTION OF ZONE 7 TO ZONE 2 STA. 0+000.00-STA.0+330.00 BARANGAY SALOGON, SAN JOSE, CAMARINES SURRoads | Completed | Camarines Sur 4th DEO | SMDP CONSTRUCTION | ₱3.8M |
| 20FG0085 | 6 yrs ago | CONSTRUCTION OF SENIOR CITIZEN BUILDING, BARANGAY PUGAY, SAN JOSE, CAMARINES SURBuildings and Facilities | Completed | Camarines Sur 4th DEO | HRB CONSTRUCTION | ₱2.8M |
| 20FG0095 | 6 yrs 1 mo ago | CLUSTER-V CONSTRUCTION OF WATER SUPPLY SYSTEM - LEVEL IIWater Provision and Storage | Completed | Camarines Sur 4th DEO | HI-TONE CONSTRUCTION & DEVELOPMENT CORP. (FORMERLY | ₱16.0M |
| 20FG0069 | 6 yrs 2 mo ago | DEPEDS CY-2020 BASIC EDUCATIONAL FACILITIES FUND (BEFF) BATCH 1,CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING(WITH COMMON TOILET AT EACH FLOOR)SALOGON HIGH SCHOOL, SAN JOSE, CAMARINES SURBuildings and Facilities | Completed | Camarines Sur 4th DEO | SOLERA CONSTRUCTION AND SUPPLY | ₱12.7M |
| 20FG0020 | 6 yrs 8 mo ago | CONSTRUCTION OF BYPASS AND DIVERSION ROAD, CONSTRUCTION OF JCT. NATO - SABANG COASTAL ROADP00402349LZ STA.2+661.60 - STA.3+211.60TAGAS SECTION, SAN JOSE, CAMARINES SURFlood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - Gravel | Completed | Camarines Sur 4th DEO | ALRO CONSTRUCTION & DEVELOPMENT CORP. | ₱87.1M |
| 20FG0051 | 6 yrs 8 mo ago | CONST. OF ROAD (P00440874LZ) 1. STA. 0+000.00 - STA. 0+100.00 (BRGY TINORONGAN, SAGNAY) 2. STA. 0+000.00 - STA. 0+090.00 (BRGY TAGAS, SAN JOSE) BRGY. TINORONGAN, SAGNAY AND BRGY. TAGAS, SAN JOSE, CAMARINES SURRoads | Completed | Camarines Sur 4th DEO | LIMCORE CONSTRUCTION AND SUPPLY | ₱1.9M |
| 20FG0009 | 6 yrs 8 mo ago | CONST. OF ROADS BRGY. CALALAHAN STA.0+000.00 - STA.0+225.50 BRGY. KINALANSANSECTION 1 : STA.0+000.00 - STA.0+052.30SECTION 2 : STA.0+000.00 - STA.0+008.15SECTION 3 : STA.0+000.00 - STA.0+044.00BRGY. CALALAHAN AND KINALANSAN, SAN JOSE, CAM. SURRoads | Completed | Camarines Sur 4th DEO | LIMCORE CONSTRUCTION AND SUPPLY | ₱1.9M |
Records are placed by the location the source gives. Some national-level awards and DPWH contracts have no location and are not counted here.