1,457
Total listed value
₱42.79B
Distinct contractors
103

More info

Level
DPWH office
Records span
Feb 20, 2016 – Sep 15, 2026

Largest contractors

SUNWEST, INC.₱21.43B

The largest contractor holds 50.1% of this office's listed value.

Latest 25 from a total of 1,457 records
Contract IDStartDescriptionStatusContractorAmount
24EH00222 yrs 8 mo agoCONSTRUCTION OF SITIO LUPOG TO SITIO BARIRI ROAD, FERROL, ROMBLONGAA 2024 SSPCompletedSUNWEST, INC.₱144.7M
24EH00422 yrs 8 mo agoCONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG TABLAS CIRCUMFERENTIAL RD, K0022+624 - K0022+990.42 (AS PER RBIA), K0022+636 - K0023+002.42 (AS PER ACTUAL), TABLAS ISLAND, ROMBLONGAA 2024 OO-1CompletedEMQ DESIGN & CONSTRUCTION₱4.9M
24EH00482 yrs 8 mo agoREHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG ROMBLON COGON SABLAYAN ROAD, K0001+000 - K0002+000 AS PER ACTUAL AND RBIA, ROMBLON ISLAND, ROMBLONGAA 2024 OO-1CompletedEMQ DESIGN & CONSTRUCTION₱55.1M
24EH00672 yrs 8 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, SAN AGUSTIN, ROMBLON - PHASE 3, POBLACION, SAN AGUSTIN, ROMBLONGAA 2024 SSPCompletedLEGACY CONSTRUCTION CORPORATION (FORMERLY: LEGACY CONSTRUCTION)₱29.7M
24EH00692 yrs 8 mo agoIMPROVEMENT OF CANTINGAS RIS DRAINAGE SYSTEM, SAN FERNANDO, ROMBLONGAA 2024 OO-2CompletedR.G. FLORENTINO CONST. & TRADING INC.₱19.6M
24EH00832 yrs 8 mo agoCONSTRUCTION OF QUALITY ASSURANCE LABORATORY BUILDING, DPWH ROMBLON DEO, ODIONGAN, ROMBLONGAA 2024 LPCompletedE.K. CO CONSTRUCTION AND SUPPLY₱3.6M
24EH00932 yrs 8 mo agoCOMPLETION OF MULTI-PURPOSE BUILDING AT BACHAWAN, SAN AGUSTIN, ROMBLONGAA 2024 SSPCompletedEMQ DESIGN & CONSTRUCTION₱5.0M
24EH00942 yrs 8 mo agoCONSTRUCTION OF ACCESS ROAD LEADING TO BLUE HOLE DIVE SITE PHASE II, BRGY. CAWAYAN, SAN AGUSTIN, ROMBLONGAA 2024 SSPCompletedEMQ DESIGN & CONSTRUCTION₱9.9M
24EH00982 yrs 8 mo agoCONSTRUCTION OF PANIQUE FLOOD CONTROL ALONG PANIQUE BR. I, PANIQUE, ODIONGAN, ROMBLONGAA 2024 OO-2CompletedSCATR CONSTRUCTION₱96.5M
24EH00992 yrs 8 mo agoCONSTRUCTION OF LIBERTAD FLOOD CONTROL STRUCTURE (DOWNSTREAM) LIBERTAD, ODIONGAN, ROMBLONGAA 2024 OO-2CompletedSCATR CONSTRUCTION₱109.4M
24EH01042 yrs 8 mo agoCONSTRUCTION OF BATIANO FLOOD CONTROL PHASE 2 (DOWNSTREAM), BATIANO, ODIONGAN, ROMBLONGAA 2024 OO-2CompletedSCATR CONSTRUCTION₱96.5M
24EH01122 yrs 8 mo agoCONSTRUCTION OF BAITO FLOOD CONTROL STRUCTURE PHASE 2, POCTOY, ODIONGAN, ROMBLONGAA 2024 OO-2CompletedSCATR CONSTRUCTION₱96.5M
23EH01752 yrs 8 mo agoCONSTRUCTION OF SEAWALL/CAUSEWAY LEADING TO POBLACION PHASE 2, ODIONGAN, ROMBLONUnprogrammed Appropriations 2023CompletedSUNWEST, INC.₱96.5M
23EH01762 yrs 8 mo agoCONSTRUCTION OF SHORE PROTECTION/CAUSEWAY LEADING TO SEAPORT ALONG POBLACION, CAJIDIOCAN PHASE 2, CAJIDIOCAN, ROMBLONUnprogrammed Appropriations 2023CompletedSUNWEST, INC.₱125.5M
23EH01772 yrs 8 mo agoCONSTRUCTION OF SHORE PROTECTION/CAUSEWAY LEADING TO SEAPORT ALONG POBLACION, CAJIDIOCAN PHASE 3, CAJIDIOCAN, ROMBLONUnprogrammed Appropriations 2023CompletedSUNWEST, INC.₱120.6M
23EH01782 yrs 8 mo agoCONSTRUCTION OF STORM SURGE PROTECTION/CAUSEWAY ALONG CARMEN, SAN AGUSTIN, ROMBLONUnprogrammed Appropriations 2023CompletedSUNWEST, INC.₱96.5M
24EH00632 yrs 8 mo agoCONSTRUCTION OF FLOOD CONTROL STRUCTURE, MAYHA RIVER UPSTREAM(L/S), ODIONGAN, ROMBLONGAA 2024 OO-2CompletedSUNWEST, INC.₱96.5M
24EH00642 yrs 8 mo agoCONSTRUCTION OF GABAWAN RIVER CONTROL ALONG BULWANG UPSTREAM(B/S) PHASE 2, ODIONGAN, ROMBLONGAA 2024 OO-2CompletedSUNWEST, INC.₱139.9M
24EH00652 yrs 8 mo agoCONSTRUCTION OF GABAWAN RIVER CONTROL ALONG BULWANG UPSTREAM(B/S) PHASE 3, ODIONGAN, ROMBLONGAA 2024 OO-2CompletedSUNWEST, INC.₱139.9M
24EH00702 yrs 8 mo agoCONSTRUCTION OF FLOOD CONTROL STRUCTURE, SITIO SUONG BRGY. CARMEN, SAN AGUSTIN, ROMBLONGAA 2024 OO-2CompletedSUNWEST, INC.₱96.5M
24EH00712 yrs 8 mo agoCONSTRUCTION OF FLOOD CONTROL STRUCTURE, SITIO AGCAHICO BRGY. CARMEN, SAN AGUSTIN, ROMBLONGAA 2024 OO-2CompletedSUNWEST, INC.₱96.5M
24EH00722 yrs 8 mo agoCONSTRUCTION OF RIVER CONTROL AT MAYOR RIVER, BINONGA-AN, SAN AGUSTIN, ROMBLONGAA 2024 OO-2CompletedSUNWEST, INC.₱96.5M
24EH00742 yrs 8 mo agoCONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MAYHA RIVER - PHASE 2, ODIONGAN, ROMBLONGAA 2024 OO-2CompletedSUNWEST, INC.₱139.9M
24EH00802 yrs 8 mo agoCONSTRUCTION OF MAINIT (DS-LS) FLOOD CONTROL STRUCTURE, ODIONGAN, ROMBLONGAA 2024 OO-2CompletedSUNWEST, INC.₱135.1M
24EH00812 yrs 8 mo agoCONSTRUCTION OF MAINIT (DS-RS) FLOOD CONTROL STRUCTURE, ODIONGAN, ROMBLONGAA 2024 OO-2CompletedSUNWEST, INC.₱139.9M