Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23EH0177

DPWH infrastructure contract
Contract ID:
23EH0177
Fingerprint:
fb65b5f3cea55e…57593287a0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 13, 2024 (2 yrs 8 mo ago) · Target/actual end Nov 15, 2024
Description:
CONSTRUCTION OF SHORE PROTECTION/CAUSEWAY LEADING TO SEAPORT ALONG POBLACION, CAJIDIOCAN PHASE 3, CAJIDIOCAN, ROMBLON
Category:
Unprogrammed Appropriations 2023
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
SUNWEST, INC. · DPWH contractor code 15906
As listed: SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION)
Contract amount:
₱120,625,000.00 (₱120.6M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2023
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
165ddb6d7696…Feb 22, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ROMBLON DEO₱117,851,015.47

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25EH0031May 26, 2025CONSTRUCTION OF CAMBALO FLOOD CONTROL STRUCTURE, CAJIDIOCAN, ROMBLONOn-Going₱48.3M
25EH0115May 23, 2025COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY DANAO, CAJIDIOCAN, ROMBLONOn-Going₱4.9M
25EH0135May 22, 2025CONCRETING OF SITIO ALAHAG, BRGY. DANAO, FMR, BRGY. DANAO, CAJIDIOCAN, ROMBLONOn-Going₱39.1M
25EH0039Apr 11, 2025CONSTRUCTION OF TAGUILOS CIS, SLOPE PROTECTION WORKS (UPSTREAM AND DOWNSTREAM, LEFT AND RIGHT SIDE EMBANKMENT), CAJIDIOCAN, ROMBLONCompleted₱9.7M
25E00263Apr 6, 2025SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. CAMBIJANG-BRGY. POBLACION, STA. 000+748.60-STA. 001+020, CAJIDIOCAMN, ROMBLONOn-Going₱230.9M
25E00264Apr 6, 2025SUSTAINABLE INFRASTRUCTURE ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. CAMBIJANG, STA. 000+398.65-STA. 000+440; STA. 000+520-STA. 000+740, CAJIDIOCAN, SIBUYAN ISOn-Going₱230.9M
25EH0028Mar 25, 2025ACCESS ROAD LEADING TO CAJIDIOCAN VIEWDECK, CAJIDIOCAN, ROMBLONCompleted₱9.6M
24EH0179Mar 24, 2025CONSTRUCTION OF LUMBANG WESTE FLOOD CONTROL STRUCTURE ALONG LUMBANG RIVER PHASE 2, CAJIDIOCAN, ROMBLONOn-Going₱130.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.