FY2026 GAA: ₱6.79T
PisoScan

DPWH Flood Control Management Cluster

DPWH implementing office 5d1fe56eccff795dad1b

Overview

DPWH contracts
192
Total listed value
₱45.39B
Distinct contractors
76

More info

Level
DPWH office
Location
Not stated
Records span
May 10, 2016 – Mar 14, 2024

Largest contractors

Latest 25 from a total of 192 records
Contract IDStartDescriptionStatusContractorAmount
18C000528 yrs agoDREDGING OF GUAGUA-PASAC RIVER, SASMUAN, PAMPANGAFlood Control and DrainageCompletedAARCON BUILDERS (28336) / PREMIUM MEGASTRUCTURES INC.₱187.5M
18O000298 yrs agoUPGRADING OF LONGOS PUMPING STATIONS 1 AND 2 (PHASE 2), MALABON CITYFlood Control and DrainageCompletedE.F. CHUA CONSTRUCTION, INC.₱95.2M
18C000548 yrs 1 mo agoCONSTRUCTION OF GROUNDSILLS ACROSS PASIG-POTRERO RIVER AT DOWNSTREAM OF MANCATIAN BRIDGE, ANGELES-PORAC RIVER AT DOWNSTREAM OF MANCATIAN BRIDGE (GROUNDSILL NO. 1), ANGELES-PORAC, PAMPANGAFlood Control and DrainageCompletedNORTHERN BUILDERS₱309.6M
18C000498 yrs 1 mo agoCONSTRUCTION OF LAYAC DIVERSION CHANNEL INCLUDING ROW, DINALUPIHAN, BATAAN.Flood Control and DrainageCompletedNORTHERN BUILDERS₱137.5M
18C000478 yrs 3 mo agoFLOOD CONTROL WORKS-ABACAN RIVER DIKING AND SLOPE PROTECTION WORKS, MEXICO, PAMPANGAFlood Control and DrainageCompletedR.U. AQUINO CONSTRUCTION AND DEVELOPMENT CORP. (FO₱761.0M
18C000518 yrs 3 mo agoCONSTRUCTION OF FLOOD CONTROL WORKS ALONG SAPANG BAYU AND SAPANG MARAGUL, LUBAO AND STA. RITA, PAMPANGAFlood Control and DrainageCompletedTOKWING CONSTRUCTION, CORP.(FOR; TOKWING CONSTRUC₱94.0M
18C000448 yrs 6 mo agoREHABILITATION/RESTORATION OF DETERIORATED DIKES/ERODED RIVERBANKS ALONG PAMPANGA RIVER INCLUDING CANDABA CUT-OFF CHANNEL, CANDABA, PAMPANGA (INLCUDING ROW), CANDABA AND SAN SIMON, PAMPANGAFlood Control and DrainageCompletedEDDMARI CONSTRUCTION & TRADING₱174.3M
18C000458 yrs 6 mo agoREHABILITATION OF PAMPANGA RIVER BASIN AT BARANGAY STA. CRUZ AND SAN NICOLAS, SAN SIMON, PAMPANGAFlood Control and DrainageCompletedD.L CERVANTES CONSTRUCTION CORPORATION (FORMERLY: (13799) / FERDSTAR BUILDERS INC.₱111.7M
18C000468 yrs 6 mo agoDIKING WITH SLOPE PROTECTION SACOBIA-BAMBAN RIVER, BAMBAN, TARLACGAA 2018 OO-2Completed11-16 CONSTRUCTION (29646) / D.L CERVANTES CONSTRUCTION CORPORATION (FORMERLY:₱99.4M
18C000488 yrs 6 mo agoREHABILITATION OF CABIAO-SAN ISIDRO RING LEVEE, CABIAO AND SAN ISIDRO, NUEVA ECIJAGAA 2018 OO-2CompletedGVDPM CONSTRUCTION CORP. (FORMERLY: ZM CONSTRUCTIO (9052) / R.A. PAHATI CONST. & SUPPLY, INC.₱143.4M
17Z000108 yrs 6 mo agoRAISING OF FOLDER DIKE INCLUDING SLOPE PROTECTION WORKS (PHASE 4: STA 2+030 TO STA. 2+530, PHASE 5: STA. 5+720 TO STA. 5+200, PHASE 6) BRGY. DAMPALIT, MALABON CITYGAA 2017 MFO-2On-GoingCOCO TECHNOLOGIES CORPORATION (35673) / E.M. CUERPO, INC. (30963) / G.G. UY CONSTRUCTION₱284.5M
16O000478 yrs 6 mo agoFLOOD CONTROL PROJECTS BAS3ED ON FLOOD MASTER PLAN FOR METRO MANILA AND SURROUNDING AREAS, LAS PINAS RIVER IMPROVEMENT INCLUDING ROW (REVETMENT WORKS ALONG MARULAS-TUNGTONG CREEK DIVERSION CHANNEL (DPWH: KAYBUBOY CREEK TRIBUTARY)STA. 1+100 TO STA. 1+400,Flood Control and DrainageCompletedE.F. CHUA CONSTRUCTION, INC.₱114.9M
16Z000188 yrs 7 mo agoFLOOD CONTROL PROJECT BASED ON MASTER PLAN FOR METRO MANILA AND SURROUNDING AREAS, UPPER MARIKINA RIVER IMPROVEMENT (UPSTREAM OF MARIKINA BRIDGE)BridgesTerminatedCIRIACO CORPORATION₱0
17Z000218 yrs 7 mo agoPASIG MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT, PHASE V, CONTRACT PACKAGE 9 - CONSTRUCTION OF MALANDAY PUMPING STATION AND ASSOCIATED WORKS, MARIKINA CITYFlood Control and DrainageOn-GoingJ.D. LEGASPI CONSTRUCTION (9608) / S.A. PLEYTO CONSTRUCTION CORPORATION₱399.5M
17Z000118 yrs 7 mo agoREHABILITATION OF NAPINDAN HYDRAULIC CONTROL STRUCTURES THROUGH DESIGN AND BUILD SCHEME, BRGY. BUTING, PASIG CITYFlood Control and DrainageCompletedA.M. ORETA & CO., INC. (108) / E. F. CHUA CONSTRUCTION, INC.₱849.1M
16O000498 yrs 8 mo agoVALENZUELA-PUMPING STATIONS IN VALENZUELA WAWANG POLO AND COLOONG PUMPING STATIONS (COLOONG PUMPING STATION ACCESS ROAD), COLOONG VALENZUELA CITYRoadsCompletedTRIPLE 8 CONSTRUCTION & SUPPLY, INC. (FORMERLY TRIPLE 8 CONST. & SUPPLY)₱91.8M
17OF01988 yrs 8 mo agoCONSTRUCTION OF RETARDING POND, KAINGIN BUKID, BRGY. APOLONIO SAMSON, QUEZON CITY 6TH LD (PROPOSED INTERCEPTOR ALONG TOCTOCAN ROAD, STA. 0+005.324 - STA. 0+484.093), Q.C.Flood Control and DrainageOn-GoingR.U. AQUINO CONSTRUCTION AND DEVELOPMENT CORP. (FO₱247.1M
16Z000218 yrs 8 mo agoMETRO CEBU FLOOD CONTROL PROJECT AND DRAINAGE IMPROVEMENT PROJECT - SUBANG DAKU, LAHUG, GUADALUPE, KINALUMSAN, TIPOLO, TEJERO AND BULACAO RIVER BASINS, CEBU CITYFlood Control and DrainageOn-GoingARN BUILDERS, INC.₱684.0M
17OB04768 yrs 8 mo agoPASIG-MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT PHASE IV (CONTRACT PACKAGE NO. 2) MIDDLE MARIKINA RIVER IMPROVEMENT WORKS, LEFT BANK, STA. 7+235 TO STA. 7+335GAA 2016 MFO-2TerminatedMSB VITUG CONSTRUCTION INC. (FORMERLY MSB VITUG CONSTRUCTION)₱67.1M
17Z000208 yrs 8 mo agoPASIG MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT, PHASE V, CONTRACT PACKAGE 8 - RIVER IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER (UPSTREAM OF MARIKINA BRIDGE) STA. 18+650 TO STA. 19+350, LEFT AND RIGHT BANKS, MARIKINA CITYGAA 2017 MFO-2On-GoingFERDSTAR BUILDERS INC. (4965) / R.U. AQUINO CONSTRUCTION AND DEVELOPMENT CORP. (FO₱652.3M
17Z000198 yrs 9 mo agoPASIG MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT, PHASE V, CONTRACT PACKAGE 6 - RIVER IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER (UPSTREAM OF MARIKINA BRIDGE) STA. 17+450 TO STA. 18+130, LEFT AND RIGHT BANKS, MARIKINA CITYFlood Control and DrainageCompletedTOKWING CONSTRUCTION, CORP.(FOR; TOKWING CONSTRUC₱689.3M
16Z000208 yrs 9 mo agoCONSTRUCTION OF RETARDING POND, KAINGIN BUKID, BRGY. APOLONIO SAMSON, QUEZON CITY 6TH LDFlood Control and DrainageOn-GoingR.U. AQUINO CONSTRUCTION AND DEVELOPMENT CORP. (FO₱942.7M
17Z000188 yrs 9 mo agoPASIG MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT, PHASE V, CONTRACT PACKAGE 5 - RIVER IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER (UPSTREAM OF MARIKINA BRIDGE) STA. 16+050 TO STA. 17+450, LEFT BANK, MARIKINA CITYGAA 2017 MFO-2CompletedAKN CONSTRUCTION CORPORATION₱294.1M
17Z000228 yrs 9 mo agoPASIG MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT, PHASE V, CONTRACT PACKAGE 2 AND 3 - RIVER IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER UPSTREAM OF MARIKINA BRIDGE) STA. 14+100 TO STA. 15+450, LEFT BANK, MARIKINA CITYGAA 2017 MFO-2CompletedMSB VITUG CONSTRUCTION INC. (FORMERLY MSB VITUG CONSTRUCTION)₱777.2M
17Z000238 yrs 9 mo agoMETRO CEBU FLOOD CONTROL PROJECT AND DRAINAGE IMPROVEMENT PROJECT - SUBANG DAKU, LAHUG, GUADALUPE AND BULACAO RIVER BASINS, CEBU CITYGAA 2017 MFO-2CompletedM.E. SICAT CONSTRUCTION, INC. (FORMERLY M.E. SICAT (16724) / MSB VITUG CONSTRUCTION INC. (FORMERLY MSB VITUG CONSTRUCTION)₱142.1M