| Record ID | Reference | Age | Project title | Awarded to | Amount |
|---|---|---|---|---|---|
| 923529241719… | 2018-1308-001 | 8 yrs 2 mo ago | Construction of Covered Court, Phase III | LJPM BUILDERS & CONST. SUPPLY | ₱197.3K |
| 6095b6f720b4… | 2018-1308-001 | 8 yrs 2 mo ago | Construction of Covered Court, Phase III | LJPM BUILDERS & CONST. SUPPLY | ₱197.3K |
| 3d16e2307f73… | 2018-1308-001 | 8 yrs 2 mo ago | Construction of Covered Court, Phase III | LJPM BUILDERS & CONST. SUPPLY | ₱197.3K |
| 20aa37dc0045… | 2018-1308-001 | 8 yrs 2 mo ago | Construction of Covered Court, Phase III | LJPM BUILDERS & CONST. SUPPLY | ₱197.3K |
| 1aa676dc5213… | 2018-1308-001 | 8 yrs 2 mo ago | Construction of Covered Court, Phase III | LJPM BUILDERS & CONST. SUPPLY | ₱197.3K |
| bb4caef75536… | 2018-1308-001 | 8 yrs 2 mo ago | Construction of Covered Court, Phase III | LJPM BUILDERS & CONST. SUPPLY | ₱197.3K |
| eafea534702c… | 2018-1308-001 | 8 yrs 2 mo ago | Construction of Covered Court, Phase III | LJPM BUILDERS & CONST. SUPPLY | ₱197.3K |
| 65fb6091dc8a… | 2017-2711-002 | 8 yrs 11 mo ago | Rehabilitation of Social Center Covered Court, Phase II | LJPM BUILDERS & CONST. SUPPLY | ₱127.6K |
| 31adc843cf5c… | 2017-2711-002 | 8 yrs 11 mo ago | Rehabilitation of Social Center Covered Court, Phase II | LJPM BUILDERS & CONST. SUPPLY | ₱127.6K |
| aa0a9fdc59ef… | 2017-2711-002 | 8 yrs 11 mo ago | Rehabilitation of Social Center Covered Court, Phase II | LJPM BUILDERS & CONST. SUPPLY | ₱127.6K |
| d96bdaf4a41e… | 2017-2711-002 | 8 yrs 11 mo ago | Rehabilitation of Social Center Covered Court, Phase II | LJPM BUILDERS & CONST. SUPPLY | ₱127.6K |
| 157627c785ca… | 2017-2711-002 | 8 yrs 11 mo ago | Rehabilitation of Social Center Covered Court, Phase II | LJPM BUILDERS & CONST. SUPPLY | ₱127.6K |
| 15b8f2f27ae0… | 2017-2711-002 | 8 yrs 11 mo ago | Rehabilitation of Social Center Covered Court, Phase II | LJPM BUILDERS & CONST. SUPPLY | ₱127.6K |
| e259fdd3f7de… | 2017-2709-001 | 9 yrs 1 mo ago | Rehabilitation of Social Center Covered Court, Phase 1 | LJPM BUILDERS & CONST. SUPPLY | ₱197.6K |
| 7d85454a7e0f… | 2017-2709-001 | 9 yrs 1 mo ago | Rehabilitation of Social Center Covered Court, Phase 1 | LJPM BUILDERS & CONST. SUPPLY | ₱197.6K |
| 5ce16b252e29… | 2017-2709-001 | 9 yrs 1 mo ago | Rehabilitation of Social Center Covered Court, Phase 1 | LJPM BUILDERS & CONST. SUPPLY | ₱197.6K |
| 2fb112bf88f5… | 2017-2709-001 | 9 yrs 1 mo ago | Rehabilitation of Social Center Covered Court, Phase 1 | LJPM BUILDERS & CONST. SUPPLY | ₱197.6K |
| 1f27312c3961… | 2017-2709-001 | 9 yrs 1 mo ago | Rehabilitation of Social Center Covered Court, Phase 1 | LJPM BUILDERS & CONST. SUPPLY | ₱197.6K |
| c91db98669dc… | 2017-2709-001 | 9 yrs 1 mo ago | Rehabilitation of Social Center Covered Court, Phase 1 | LJPM BUILDERS & CONST. SUPPLY | ₱197.6K |