KOUZBARY BUILDERS
Contractor 04a6e148d2008fdb2cdf
Overview
PhilGEPS awards
₱10.11B · 117 awards
DPWH contracts
₱5.20B · 65 contracts
Rank by recorded value
#207 of 23,487
More info
First record
Mar 2, 2015 (11 yrs 8 mo ago)
Latest record
Aug 17, 2026 (3 mos ago)
DPWH contractor code
36446
Where they work
Latest 25 from a total of 65 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 22I00036 | 4 yrs 8 mo ago | NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - MAHAPLAG - HILONGOS ROAD, PACKAGE 2, LEYTERoads | Completed | Region VIII | ₱101.1M |
| 22I00038 | 4 yrs 8 mo ago | CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) - ACCESS ROAD LEADING TO HILONGOS PORT, HILONGOS, LEYTERoads | Completed | Region VIII | ₱144.7M |
| 20Z00015 | 4 yrs 11 mo ago | CONTRACT PACKAGE 1B - REHABILITATION OF EXISTING MINDANAO STATE UNIVERSITY (MSU) ROADSGAA 2019 FAPs | On-Going | Roads Management Cluster II (Multilateral) | ₱161.1M |
| 21KG0028 | 5 yrs 6 mo ago | FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF REVETMENT/RIVERBANK PROTECTION AT PINUYAK BRIDGE ALONG MARANDING RIVER STREAM,BRGY. PINUYAK,LALA,LANAO DEL NORTEFlood Control and Drainage | Completed | Lanao del Norte 2nd DEO | ₱79.6M |
| 21I00009 | 5 yrs 7 mo ago | CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) - ACCESS ROAD LEADING TO HILONGOS PORT, HILONGOS, LEYTE, LEYTE 5TH LDRoads | Completed | Region VIII | ₱128.2M |
| 21I00003 | 5 yrs 8 mo ago | NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - MAHAPLAG - HILONGOS ROAD, PACKAGE 1, LEYTE, LEYTE, 5TH LDRoads | On-Going | Region VIII | ₱128.2M |
| 21I00004 | 5 yrs 8 mo ago | NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS, MAHAPLAG - HILONGOS ROAD, PACKAGE 2, LEYTE, LEYTE 5TH LDRoads | Completed | Region VIII | ₱128.2M |
| 21I00018 | 5 yrs 8 mo ago | NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - PALOMPON - ISABEL - MERIDA - ORMOC RD., K1119+000 - K1121+087, K1121+097.81 - K1122+492, LEYTE 4TH LDRoads | Completed | Region VIII | ₱96.2M |
| 21I00021 | 5 yrs 8 mo ago | NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS / NEW ROADS - MAHAPLAG - HILONGOS ROAD, PACKAGE 3, LEYTE 5TH LDRoads | Completed | Region VIII | ₱137.4M |
| 20I00017 | 5 yrs 11 mo ago | ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - TABANGO - CATMON - LA FORTUNA - MANLAWAAN - GIMARCO RD. - K1035+854 - K1035+947, K1034+000 - K1034+030, K1034+057 - K1034+185, LEYTE 3Roads | Completed | Region VIII | ₱91.6M |
| 20KG0023 | 6 yrs 8 mo ago | ASSET PRESERVATION-REHAB./RECONST. OF NATIONAL ROADS WITH SLIPS,SLOPE COLLPASE AND LANDSLIDE-PRIMARY ROADS, MALABANG-DOBLESTON-TUKURAN ROAD-S00931MN,K1972+500-K1972+760;K1972+910-K1973+115;K1985+275-K1985+345,SND,LANAO DEL NORTERoads | Completed | Lanao del Norte 2nd DEO | ₱50.6M |
| 20I00058 | 6 yrs 8 mo ago | NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - MAHAPLAG - HILONGOS ROAD, PACKAGE 3, LEYTE, BRGY. AGUTAYON, MAHAPLAG, LEYTERoads | Completed | Region VIII | ₱144.7M |
| 19I00122 | 7 yrs ago | CLUSTER II: 1. REPAIR/REHAB. OF DAMAGED PAVED ROADS ALONG TABANGO - CATMON - LA FORTUNA - MANLAWAAN - GIMARCO RD., K1036+800 - K1036+950, K1037+340 - K1037+500, K1037+620 - K1037+650, K1037+820 - K1038+020, K1038+150 - K1038+280, LEYTE 3RD LD; 2. REPAIR/KRoads | Completed | Region VIII | ₱125.2M |
| 18Z00040 | 7 yrs 4 mo ago | URGENT REHABILITATION OF TRANS-CENTRAL ROAD DAMAGED BY CONFLICT IN MARAWI CITY, CONRTACT PACKAGE - 2, LOCATED IN MARAWI CITY, LANAO DEL SUR USING A DESIGN AND BUILD SCHEMERoads | Completed | Roads Management Cluster I (Bilateral) | ₱139.3M |
| 19I00071 | 7 yrs 4 mo ago | NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS / NEW ROADS: MAHAPLAG - HILONGOS ROAD, PACKAGE 3, LEYTE 5TH LDRoads | Completed | Region VIII | ₱94.1M |
| 19I00090 | 7 yrs 4 mo ago | NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS / NEW ROADS: MAHAPLAG - HILONGOS ROAD, PACKAGE 1, LEYTE, CW1 - CONSTRUCTION OF CONCRETE ROAD, LEYTE 5TH LDRoads | Completed | Region VIII | ₱103.7M |
| 18K00315 | 7 yrs 11 mo ago | CONST. OF MUNICIPAL ROADS LINKING TO NARCISO RAMOS HIGHWAY (MAROGONG-MALABANG-BALABAGAN SEC), LANAORoads | Completed | Region X | ₱46.8M |
| 18K00292 | 8 yrs ago | CONST. ALONG TUBOD - GANASSI ROAD, K1611 + 000 - K1616 + 1000, LANAO DEL SUR 2NDRoads | Completed | Region X | ₱93.6M |
| 18K00297 | 8 yrs ago | REPAIR/REHAB./IMPRVT. OF MAROGONG-BALABAGAN ROAD, LANAO DEL SUR 2NDRoads | Completed | Region X | ₱210.6M |
| 18K00307 | 8 yrs ago | CONCRETING OF PALAO RANARANAO-ILIAN ROAD, MARANTAO, LANAO DEL SUR 1STRoads | Completed | Region X | ₱18.7M |
| 18KG0064 | 8 yrs 4 mo ago | REHABILITATION OF POONA KAPATAGAN-LINDONGAN FMR, TANGKAL, LANAO DEL NORTERoads | Completed | Lanao del Norte 2nd DEO | ₱39.2M |
| 18K00112 | 8 yrs 4 mo ago | CONST. OF MISSING LINKS/NEW ROADS,LDNICR(SALVADOR-SAPAD-NUNUNGAN SEC.)PACKAGE 4,LANAO DEL NORTERoads | Completed | Region X | ₱118.0M |
| 17IE0061 | 9 yrs 5 mo ago | OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, LEMON-LEYTE-BILIRAN ROAD, K0983+218-K0983+493; K0983+512-K0988+438, K0993+000-K0996+996; K1001+000-K1004+778LEYTE, LEYTERoads | Completed | Leyte 3rd DEO | ₱91.5M |
| 17IF0046 | 9 yrs 7 mo ago | IMPROVEMENT/ WIDENING OF NATIONAL ROADS - ORMOC - BAYBAY SOUTHERN LEYTE BDRY. RD K1029+460 - K1031+710, K1031+785 - K1032+000, K1034+516 - K1035+486, K1035-509 - K1037+142Roads | Completed | Leyte 4th DEO | ₱119.2M |
| 17IF0047 | 9 yrs 8 mo ago | IMPROVEMENT/ WIDENING OF NATIONAL ROADS - PALO-CARIGARA-ORMOC RD K0990+332-K0990+725; K0995+004-K0996+318; K0996+318-K0996+616; K0996+691-K0998+490; K0998+490-K0998+916Roads | Completed | Leyte 4th DEO | ₱108.5M |
Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.