Physical progress:
100%
Timeline:
Start Dec 3, 2020 (5 yrs 11 mo ago) · Target/actual end Dec 6, 2021
Description:
ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - TABANGO - CATMON - LA FORTUNA - MANLAWAAN - GIMARCO RD. - K1035+854 - K1035+947, K1034+000 - K1034+030, K1034+057 - K1034+185, LEYTE 3
Category:
Roads
Implementing office:
DPWH Region VIII · Region VIII
Contractor:
KOUZBARY BUILDERS · DPWH contractor code 36446
Contract amount:
₱91,579,937.59 (₱91.6M)
Funding source:
Regular Infra - GAA 2020 OO-1
Budget year:
2020
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IE0095 | Aug 4, 2025 | CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), COLONIA ELEMENTARY SCHOOL, TABANGO, LEYTE | On-Going | ₱322.4K |
| 25IE0060 | Jul 29, 2025 | CONSTRUCTION OF SITIO LIBUNGAO-SITIO TUBIG BAHO ROAD, BRGY. INANGATAN, TABANGO, LEYTE | Completed | ₱9.9M |
| 25IE0046 | Jul 17, 2025 | ASSET PRESERVATION REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE SECONDARY ROADS-CALUBIAN JCT. SAN ISIDRO-TABANGO-VILLABA-PALOMPON ROAD, K1037+425 K1037+571 | On-Going | ₱58.8M |
| 25IE0068 | Jun 8, 2025 | CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY SANTA ROSA, TABANGO, LEYTE | On-Going | ₱4.9M |
| 25IE0077 | May 29, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PHASE 2, BARANGAY MANLAWAAN, TABANGO, LEYTE | Completed | ₱2.0M |
| 25IE0062 | May 26, 2025 | CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY TABING, TABANGO, LEYTE | On-Going | ₱4.9M |
| 25IE0004 | Mar 24, 2025 | ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES-SECONDARY ROADS, CALUBIAN JCT-SN ISIDRO-TABANGO-VILLABA-PALOMPON RD K1026+968-K1027+039, K1037+000-K1037+072 | Completed | ₱24.4M |