RKVT CONSTRUCTION
Contractor 3743279839334cf800b3
Overview
PhilGEPS awards
₱1.14B · 42 awards
DPWH contracts
₱252.5M · 22 contracts
Rank by recorded value
#1,943 of 23,487
More info
First record
Jul 31, 2023 (3 yrs 3 mo ago)
Latest record
Sep 15, 2026 (2 mos ago)
DPWH contractor code
54400
Where they work
Latest 22 from a total of 22 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 26RE0055 | 2 mos ago | CONSTRUCTION OF DPWH NEGROS OCCIDENTAL 5TH DISTRICT ENGINEERING OFFICE (DEO) BUILDING, SAN CARLOS CITY, NEGROS OCCIDENTAL (123.436581°, 10.521394°)GAA 2026 LFP | On-Going | Negros Occidental 5th DEO | ₱29.1M |
| 26RE0056 | 2 mos ago | OFF-CARRIAGEWAY IMPROVEMENT: PAVING OF SHOULDERS ALONG BACOLOD NORTH RD - K0141 + 954 - K0143 + 120GAA 2026 OO-1 | On-Going | Negros Occidental 5th DEO | ₱19.1M |
| 25RE0019 | 1 yr 2 mo ago | CONSTRUCTION (COMPLETION) OF DPWH BUILDING OF NEGROS OCCIDENTAL SUB DEO, SAN CARLOS CITY, NEGROS OCCIDENTALGAA 2025 LFP | On-Going | Negros Occidental 5th DEO | ₱29.8M |
| 25RE0018 | 1 yr 2 mo ago | CONCRETING OF SITIO NAPATURAN, BRGY. CODCOD FMR, BRGY. CODCOD, SAN CARLOS CITY, NEGROS OCCIDENTALGAA 2025 DA FMR | Completed | Negros Occidental 5th DEO | ₱19.8M |
| 25RE0010 | 1 yr 4 mo ago | CONSTRUCTION OF SCHOOL BUILDING, BUNGA INTEGRATED SCHOOL, BARANGAY BUNGA, MUNICIPALITY OF SALVADOR BENEDICTO, NEGROS OCCIDENTALGAA 2025 DEPED BEFF | Completed | Negros Occidental 5th DEO | ₱4.9M |
| 25GQ0047 | 1 yr 5 mo ago | CONCRETING OF BRGY. PROSPERIDAD FMR, BRGY. PROSPERIDAD, SAN CARLOS CITY, NEGROS OCCIDENTALGAA 2025 DA FMR | Completed | Negros Occidental 5th DEO | ₱14.8M |
| 25RE0003 | 1 yr 5 mo ago | CONSTRUCTION OF ROAD, BARANGAY MACASILAO TO BARANGAY WINASWASAN, CALATRAVA, NEGROS OCCIDENTALGAA 2025 SSP | Completed | Negros Occidental 5th DEO | ₱9.8M |
| 25RE0005 | 1 yr 5 mo ago | CONSTRUCTION OF ROAD, BARANGAY MACASILAO TO BARANGAY CAMBAYUBO, CALATRAVA, NEGROS OCCIDENTALGAA 2025 SSP | Completed | Negros Occidental 5th DEO | ₱9.8M |
| 25RE0007 | 1 yr 5 mo ago | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - ALONG STOP AGUINALDO - BUG-ANG RD - K0111 + 847 - K0111 + 907GAA 2025 OO-1 | Completed | Negros Occidental 5th DEO | ₱7.7M |
| 25HM0061 | 1 yr 5 mo ago | CAPITAL OUTLAY - FARM-TO-MARKET ROAD (FMR) PROJECTS, REPAIR/REHABILITATION AND CONSTRUCTION OF FARM-TO-MARKET ROADS, CONCRETING OF BRGY. TALAYONG TO SITIO BONACAN FMR, BRGY. TALAYONG, LAZI, SIQUIJORGAA 2025 DA FMR | On-Going | Siquijor DEO | ₱14.6M |
| 25GQ0031 | 1 yr 7 mo ago | RECONSTRUCTION TO CONCRETE PAVEMENT ALONG JCT NATL RD SAGAY-BATO-DIAN-MARCELO-BALEA JCT RD (S00426NR) - K0108+275 - K0108+560, K0108+703 - K0109+237, K0111+360 - K0111+559, K0111+610 - K0111+736GAA 2025 OO-1 | Completed | Negros Occidental 5th DEO | ₱25.3M |
| 25GQ0032 | 1 yr 7 mo ago | REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS ALONG BACOLOD-MURCIA- DS BENEDICTO-SN CARLOS CITY RD K0053 + 150 - K0053 + 185GAA 2025 OO-1 | Completed | Negros Occidental 5th DEO | ₱4.8M |
| 25GQ0036 | 1 yr 7 mo ago | CONSTRUCTION OF ROAD, BARANGAY CODCOD TO BARANGAY QUEZON, SAN CARLOS CITY, NEGROS OCCIDENTALRoads | Completed | Negros Occidental 5th DEO | ₱19.6M |
| 25GQ0039 | 1 yr 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MARCELO, MUNICIPALITY OF CALATRAVA, NEGROS OCCIDENTALGAA 2025 SSP | On-Going | Negros Occidental 5th DEO | ₱4.9M |
| 25GQ0042 | 1 yr 7 mo ago | CONSTRUCTION OF ROAD, BARANGAY RIZAL, SAN CARLOS CITY, NEGROS OCCIDENTALRoads | Completed | Negros Occidental 5th DEO | ₱9.9M |
| 24GQ0010 | 2 yrs 4 mo ago | REHABILITATION/ MAJOR REPAIR OF ROAD SLOPE PROTECTION STRUCTURE ALONG BACOLOD NORTH RD (S00425NR)- K0109+300- K0109+347Roads | Completed | Region VI | ₱3.3M |
| 24GQ0013 | 2 yrs 4 mo ago | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG BACOLOD- MURCIA- DS BENEDICTO- SN CARLOS CITY RD (S00427NR)- K0074+809- K0074+848Roads | Completed | Region VI | ₱3.8M |
| 24GQ0017 | 2 yrs 4 mo ago | REHABILITATION/ MAJOR REPAIR OF ROAD SLOPE PROTECTION STRUCTURE ALONG JCT NATL RD SAGAY- BATO- DIAN- MARCELO- BALEA JCT RD (S00426NR)- K0105+330 - K0105+357Roads | Completed | Region VI | ₱2.8M |
| 24GQ0020 | 2 yrs 4 mo ago | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG JCT DS BENEDICTO- SPUR 16- CALATRAVA RD (S00001NR)- K0083+715- K0083+738Roads | Completed | Region VI | ₱2.4M |
| 24GQ0021 | 2 yrs 4 mo ago | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG STOP AGUINALDO- BUG- ANG RD (S00395NR)- K0113+090- K0113+160Roads | Completed | Region VI | ₱4.7M |
| 24HL0038 | 2 yrs 8 mo ago | CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER RA 11239: INSTALLATION OF SIGNAGE AND PAVEMENT MARKINGS ALONG DUMAGUETE SOUTH RD., NEGROS ORIENTALRoads | Completed | Negros Oriental 3rd DEO | ₱821.6K |
| 24HM0049 | 2 yrs 9 mo ago | OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, SIQUIJOR CIRCUMFERENTIAL RD - K0053+531 - K0053+819GAA 2024 OO-1 | On-Going | Siquijor DEO | ₱10.7M |
Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.