| Contract ID | Start | Description | Status | Office | Contractor | Amount |
|---|---|---|---|---|---|---|
| 25CC0310 | 1 yr 5 mo ago | CONSTRUCTION OF REINFORCED CONCRETE RIVER PROTECTION STRUCTURES ALONG ANGAT RIVER BARANGAY SIPAT PUROK 5, PLARIDEL, BULACAN (PACKAGE A)Flood Control and Drainage | On-Going | Bulacan 1st DEO | TOPNOTCH CATALYST BUILDERS INC. | ₱71.3M |
| 25CC0412 | 1 yr 5 mo ago | CONSTRUCTION OF REINFORCED CONCRETE RIVER PROTECTION STRUCTURES ALONG ANGAT RIVER AT BARANGAY PALTAO, PULILAN, BULACANFlood Control and Drainage | On-Going | Bulacan 1st DEO | TOPNOTCH CATALYST BUILDERS INC. | ₱47.5M |
| 25CC0418 | 1 yr 5 mo ago | REHABILITATION OF ROAD AT BARANGAY DULONG MALABON, PULILAN, BULACANRoads | On-Going | Bulacan 1st DEO | SAMJS CONSTRUCTION SERVICES | ₱7.7M |
| 25CC0434 | 1 yr 5 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY POBLACION, PULILAN, BULACANBuildings and Facilities | On-Going | Bulacan 1st DEO | SAMJS CONSTRUCTION SERVICES | ₱19.3M |
| 25CC0457 | 1 yr 5 mo ago | SIPAG - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - PULILAN-BALIUAG BYPASS ROAD - DULONG MALABON, CHAINAGE 0-CHAINAGE 1300, PULILAN, BULACANRoads | On-Going | Bulacan 1st DEO | ALPHA & OMEGA GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 38958) / JB CONSTRUCTION AND SUPPLY INC. (FORMERLY:JB CONSTRUCTION AND SUPPLY) | ₱92.6M |
| 25CC0461 | 1 yr 5 mo ago | SIPAG - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLEGU JURISDICTIONS) PULILAN-BALIUAG BYPASS ROAD - BARANGAY BALATONG B AND BARANGAY CALANTIPAY, CHAINAGE 6006-CHAINAGE 6700, BALIUAG, BULACANRoads | On-Going | Bulacan 1st DEO | L.R. TIQUI BUILDERS, INC. | ₱92.6M |
| 25CC0462 | 1 yr 5 mo ago | SIPAG - INTERJURISDICTIONAL ROADS AND/OR BRIDGES 9ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) PULILAN-BALIUAG BYPASS ROAD - BARANGAY SANTA PEREGRINA (PHASE 2), CHAINAGE 1300-CHAINAGE 3890, PULILAN, BULACANRoads | On-Going | Bulacan 1st DEO | ALPHA & OMEGA GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 38958) / JB CONSTRUCTION AND SUPPLY INC. (FORMERLY:JB CONSTRUCTION AND SUPPLY) | ₱92.6M |
| 25CC0535 | 1 yr 5 mo ago | CONSTRUCTION OF CLASSROOM BUILDING AT DAMPOL 1ST ELEMENTARY SCHOOL, BRGY. DAMPOL 1ST, PULILAN, BULACANBuildings and Facilities | On-Going | Bulacan 1st DEO | SYMS CONSTRUCTION TRADING | ₱49.4M |
| 25CC0329 | 1 yr 7 mo ago | CONSTRUCTION OF PUMPING STATION INCLUDING FLOOD GATE (PHASE II) AT BARANGAY ATLAG, MALOLOS CITY, BULACANFlood Control and Drainage | On-Going | Bulacan 1st DEO | C.T. LEONCIO CONSTRUCTION AND TRADING | ₱92.7M |
| 25CC0273 | 1 yr 7 mo ago | REHABILITATION OF MUNICIPA JAIL AND GROUNDS AT PULILAN, BULACANBuildings and Facilities | On-Going | Bulacan 1st DEO | AESIC CONSTRUCTION | ₱6.8M |
| 25CC0326 | 1 yr 7 mo ago | REHABILITATION OF SLOPE PROTECTION STRUCTURE AT BARANGAY LUMBAC. PULILAN, BULACANFlood Control and Drainage | On-Going | Bulacan 1st DEO | MICHARIAN BUILDERS AND TRADING | ₱28.2M |
| 25CC0082 | 1 yr 8 mo ago | CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG ANGAT RIVER AT BARANGAY SANTO CRISTO, PULILAN, BULACANFlood Control and Drainage | On-Going | Bulacan 1st DEO | MICHARIAN BUILDERS AND TRADING | ₱77.2M |
| 25CC0266 | 1 yr 8 mo ago | SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF DRAINAGE STRUCTURE ALONG PULILAN-BALIUAG BYPASS RD - CHAINAGE3341-7330, PULILAN, BULACANRoads | On-Going | Bulacan 1st DEO | 729 CONSTRUCTION, INC. (FORMERLY 722 CONSTRUCTION, INC.) | ₱91.1M |
| 25CC0275 | 1 yr 8 mo ago | SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF DRAINAGE STRUCTURE ALONG PULILAN-BALIUAG BYPASS RD - CHAINAGE 7330-9530, BALIUAG, BULACANRoads | On-Going | Bulacan 1st DEO | 729 CONSTRUCTION, INC. (FORMERLY 722 CONSTRUCTION, INC.) | ₱50.6M |
| 24CC0621 | 1 yr 10 mo ago | SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF STREETLIGHTS ALONG PULILAN-CALUMPIT ROAD - K0043+(-442)-K0048+253, PULILAN, BULACANRoads | On-Going | Bulacan 1st DEO | ST. GERRARD CONSTRUCTION GEN. CONTRACTOR & DEVELOPMENT CORP. (FORMERLY:ST. GERRARD CONSTRUCTION) ([REVOKED] 31762) | ₱92.6M |
| 24CC0593 | 1 yr 10 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, PACKAGE B, BARANGAY TAAL-BARANGAY SANTO CRISTO, PULILAN, BULACANFlood Control and Drainage | On-Going | Bulacan 1st DEO | WAWAO BUILDERS | ₱92.5M |
| 24CC0331 | 2 yrs 4 mo ago | IMPROVEMENT OF ROAD, BRGY. TINEJERO, PULILAN, BULACANRoads | Completed | Bulacan 1st DEO | BIG BEN CONSTRUCTION | ₱19.7M |
| 24CC0489 | 2 yrs 4 mo ago | CONCRETING OF BRGY. INAON FMR, BRGY. INAON, PULILAN, BULACANRoads | Completed | Bulacan 1st DEO | AESIC CONSTRUCTION | ₱19.9M |
| 24CC0503 | 2 yrs 5 mo ago | NETWORK DEVELOPMENT PROGRAM-OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - PULILAN-CALUMPIT RD - K0049+(-316) - K0050+018, K0050+033- K0052+287, PULILAN AND CALUMPIT, BULACANRoads | On-Going | Bulacan 1st DEO | IM CONSTRUCTION CORPORATION | ₱46.6M |
| 24CC0468 | 2 yrs 5 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, LUMANG BAYAN SECTION, PLARIDEL, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | WAWAO BUILDERS | ₱96.5M |
| 24CC0479 | 2 yrs 5 mo ago | CONCRETING OF BRGY. PUNGO FMR, BRGY. PUNGO, CALUMPIT, BULACANRoads | Completed | Bulacan 1st DEO | TBB CONSTRUCTION CORP. | ₱14.9M |
| 24CC0480 | 2 yrs 5 mo ago | CONCRETING OF BRGY. PENABATAN FMR, BRGY. PENABATAN, PULILAN, BULACANRoads | Completed | Bulacan 1st DEO | PTM DEVELOPMENT CORP. | ₱24.9M |
| 24CC0388 | 2 yrs 5 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, POLYTECHNIC UNIVERSITY OF PHILIPPINES, PULILAN, BULACANBuildings and Facilities | Completed | Bulacan 1st DEO | J.A SANDE BUILDERS AND TRADING | ₱9.9M |
| 24CC0423 | 2 yrs 5 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | 729 CONSTRUCTION, INC. (FORMERLY 722 CONSTRUCTION, INC.) | ₱96.5M |
| 23CC0593 | 2 yrs 6 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. STO. CRISTO, PULILAN, BULACANBuildings and Facilities | On-Going | Bulacan 1st DEO | DOUBLE Z CONSTRUCTION AND SUPPLY | ₱4.7M |