Dinalungan
Region III (Central Luzon) ›Aurora › City / municipality · PSGC 0307704000
Contract awards located here
0
₱0 listed value · PhilGEPS
DPWH contracts located here
138
₱2.63B contract value
COA audit opinion
138 DPWH contracts
| Contract ID | Start | Description | Status | Office | Contractor | Amount |
|---|---|---|---|---|---|---|
| 25CN0089 | 1 yr 4 mo ago | CONSTRUCTION OF ROAD, BARANGAY PALEG, DINALUNGAN, AURORAGAA 2025 SSP | Completed | Aurora DEO | SO CONSTRUCTION | ₱34.3M |
| 25CN0023 | 1 yr 5 mo ago | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, SALA BR. (B04212LZ) ALONG BALER-CASIGURAN RD (DINADIAWAN-CASIGURAN SECT)Bridges | On-Going | Aurora DEO | R.N.G.M. CONSTRUCTION CORPORATION (FORMERLY: R.N.G.M. CONSTRUCTION) | ₱14.5M |
| 25CN0122 | 1 yr 5 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY POBLACION ZONE II, DINALUNGAN, AURORAGAA 2025 SSP | Completed | Aurora DEO | JAVEN CONSTRUCTION | ₱5.9M |
| 25CN0147 | 1 yr 5 mo ago | CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY MAPALAD, DINALUNGAN, AURORAGAA 2025 SSP | Completed | Aurora DEO | RADIANCE TRADERS & BUILDERS | ₱5.0M |
| 25C00472 | 1 yr 7 mo ago | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONST./IMPR'VT. OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-DINADIAWAN-DITAWINI BYPASS ROAD LEAD. TO TOURISM SITES/DESTINATIONS, BRGY. DITAWINI, DINALUNGAN, AURoads | On-Going | Region III | ZF CONSTRUCTION | ₱14.3M |
| 25CN0006 | 1 yr 7 mo ago | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS BALER - CASIGURAN RD (DINADIAWAN-CASIGURAN SECT) K0302+000 - K0302+520Roads | Completed | Aurora DEO | ZF CONSTRUCTION | ₱18.1M |
| 25CN0088 | 1 yr 7 mo ago | CONSTRUCTION OF ROAD, BARANGAY NIPOO, DINALUNGAN, AURORAGAA 2025 SSP | Completed | Aurora DEO | RADIANCE TRADERS & BUILDERS | ₱19.3M |
| 25CN0090 | 1 yr 7 mo ago | CONSTRUCTION OF ROAD, BARANGAY POBLACION ZONE II, DINALUNGAN, AURORAGAA 2025 SSP | On-Going | Aurora DEO | RADIANCE TRADERS & BUILDERS | ₱9.7M |
| 25CN0103 | 1 yr 8 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY POBLACION ZONE II, DINALUNGAN, AURORAGAA 2025 SSP | Completed | Aurora DEO | GERRA CONSTRUCTION INCORPORATED | ₱48.3M |
| 25CN0121 | 1 yr 8 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY DITAWINI, DINALUNGAN, AURORAGAA 2025 SSP | Completed | Aurora DEO | ALEXI LOUISSE CONSTRUCTION AND GENERAL MERCHANDISE | ₱6.9M |
| 25CN0106 | 1 yr 8 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY DIBARAYBAY, DINALUNGAN, AURORAGAA 2025 SSP | Completed | Aurora DEO | JAVEN CONSTRUCTION | ₱9.9M |
| 24C00551 | 2 yrs 3 mo ago | CONVERGENCE & SPL. SUPP. PROG.-CONST./IMPR'VT. OF ACCESS RDS. LEAD. TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRA. PROG.-TRIP), DINADIAWAN-DITAWINI BYPASS ROAD LEAD. TO TOURISM SITES/DESTINATIONS, BRGY. DITAWINI, DINALUNGAN, PROV. OF AURORARoads | On-Going | Region III | ZF CONSTRUCTION | ₱97.0M |
| 24CN0155 | 2 yrs 3 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BRGY. MAPALAD, DINALUNGAN, AURORAGAA 2024 SSP | On-Going | Aurora DEO | ZF CONSTRUCTION | ₱14.8M |
| 24CN0209 | 2 yrs 3 mo ago | CONCRETING OF BRGY. NIPOO FMR PHASE II, BRGY. NIPOO, DINALUNGAN, AURORAGAA 2024 DA FMR | Completed | Aurora DEO | SO CONSTRUCTION | ₱25.9M |
| 24CN0104 | 2 yrs 3 mo ago | REHABILITATION OF MULTI-PURPOSE FACILITY (MUNICIPAL TRANSPORT TERMINAL), POBLACION ZONE II, DINALUNGAN, AURORABuildings and Facilities | On-Going | Aurora DEO | ADROIT EJD CONSTRUCTION CORP. (FORMERLY: ADROIT CONSTRUCTION) (11169) / VANMARVIL CONSTRUCTION | ₱43.6M |
| 24CN0173 | 2 yrs 3 mo ago | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE FACILITY (SANITARY LANDFILL), BRGY. DIBARAYBAY, DINALUNGAN, AURORABuildings and Facilities | Completed | Aurora DEO | DALCON CONSTRUCTION | ₱34.6M |
| 24C00564 | 2 yrs 3 mo ago | CONVERGENCE & SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM-INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF DINADIAWAN-DITAWINI BYPASS ROAD, DINADIAWAN, AURORA (PHASE 3), PROV. OF AURORRoads | On-Going | Region III | CAVACON CORPORATION (FORMERLY CAGAYAN VALLEY CONST | ₱144.0M |
| 24CN0168 | 2 yrs 4 mo ago | IMPROVEMENT OF OLD MUNICIPAL HALL, BRGY. POBLACION ZONE II, DINALUNGAN, AURORAGAA 2024 SSP | Completed | Aurora DEO | RADIANCE TRADERS & BUILDERS | ₱9.9M |
| 24CN0145 | 2 yrs 5 mo ago | CONSTRUCTION OF HIGHWAY TO DILEBSONG ROAD, BRGY. NIPOO, DINALUNGAN, AURORAGAA 2024 SSP | Completed | Aurora DEO | SO CONSTRUCTION | ₱19.8M |
| 24CN0193 | 2 yrs 5 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (DINALUNGAN MUNICIPAL HALL), BRGY. ZONE II, DINALUNGAN, AURORAGAA 2024 SSP | Completed | Aurora DEO | RADIANCE TRADERS & BUILDERS | ₱17.8M |
| 24CN0061 | 2 yrs 6 mo ago | CONSTRUCTION OF ROAD, POBLACION ZONE II, DINALUNGAN, AURORARoads | Completed | Aurora DEO | RADIANCE TRADERS & BUILDERS | ₱3.8M |
| 24CN0129 | 2 yrs 6 mo ago | CONSTRUCTION OF ROAD, BRGY. DINADIAWAN, DIPACULAO, AURORAGAA 2024 SSP | Completed | Aurora DEO | A.I.M. CONSTRUCTION | ₱9.9M |
| 24CN0154 | 2 yrs 6 mo ago | CONSTRUCTION OF SEA WALL, BRGY. NIPOO, DINALUNGAN, AURORAGAA 2024 SSP | Completed | Aurora DEO | ZF CONSTRUCTION | ₱34.6M |
| 24CN0058 | 2 yrs 6 mo ago | CONSTRUCTION OF ROAD, BRGY. NIPOO, DINALUNGAN, AURORAGAA 2024 SSP | Completed | Aurora DEO | SO CONSTRUCTION | ₱22.0M |
| 24CN0063 | 2 yrs 6 mo ago | CONSTRUCTION OF ROAD, SO. DILAGDES, BRGY. MAPALAD, DINALUNGAN, AURORAGAA 2024 SSP | Completed | Aurora DEO | SO CONSTRUCTION | ₱34.7M |
Records are placed by the location the source gives. Some national-level awards and DPWH contracts have no location and are not counted here.