Project 15AI0384

DPWH infrastructure contract
Contract ID:
15AI0384
Fingerprint:
219f01acf5a5e8…4e3edbb913 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 8, 2016 (10 yrs 9 mo ago) · Target/actual end Jun 6, 2016
Description:
CONST/MAINT OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEM-AGNO RIVER BASIN FLOOD CTRL PROJ-REHAB/
Category:
Flood Control and Drainage
Implementing office:
Contractor:
R.R. RICAFORT CONSTRUCTION AND SUPPLIES · DPWH contractor code 14402
Contract amount:
₱18,814,525.11 (₱18.8M)
Funding source:
Regular Infra - GAA 2016 MFO-2
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
860b64dfaa3a…Jan 20, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN 3RD DEO₱18,814,526.64

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.