Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 15AI0407

DPWH infrastructure contract
Contract ID:
15AI0407
Fingerprint:
f31d962f7cfd77…4c2ff2d570 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 8, 2016 (10 yrs 9 mo ago) · Target/actual end Apr 7, 2016
Description:
CONST/MAINT OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEM-AGNO RIVER BASIN FLOOD CTRL PROJ-CONSTN
Category:
Flood Control and Drainage
Implementing office:
Contractor:
ARCINUE COMM'L. CORPORATION · DPWH contractor code 6746
As listed: ARCINUE COMM'L CORPORATION
Contract amount:
₱4,798,858.61 (₱4.8M)
Funding source:
Regular Infra - GAA 2016 MFO-2
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
02e474dfd0cc…Jan 20, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN 3RD DEO₱4,798,858.61

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.