FY2026 GAA: ₱6.79T
PisoScan

Project 15CD0224

DPWH infrastructure contract
Contract ID:
15CD0224
Fingerprint:
7394112d1254dc…c3ab498524 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 12, 2016 (10 yrs 7 mo ago) · Target/actual end Jun 10, 2016
Description:
CONSTRUCTION/IMPROVEMENT OF BARANGAY HALL, CIUDAD REAL, SAN JOSE DEL MONTE CITY, BULACAN
Category:
Buildings and Facilities
Implementing office:
DPWH Bulacan 2nd DEO · Region III
Contractor:
MANUEL A. DELA TORRE JR. BUILDERS · DPWH contractor code 31024
As listed: MANUEL A. DELA TORRE, JR. BUILDERS
Contract amount:
₱949,305.90 (₱949.3K)
Funding source:
Regular Infra - GAA 2016 Locally Funded Projects
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
66884ee46815…Jan 25, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 2ND DEO₱949,305.90

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25OD0370Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, NORTH OLYMPUS, BARANGAY 172, CALOOCAN CITYOn-Going₱9.2M
25OD0371Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 156, CALOOCAN CITYOn-Going₱10.5M
25OD0373Jul 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), CELINA HOMES, BARANGAY 168, CALOOCAN CITYOn-Going₱4.8M
25OD0374Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PHASE 2, BARANGAY 171, CALOOCAN CITYCompleted₱4.8M
25OD0375Jul 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX), BARANGAY 176, CALOOCAN CITY (PHASE 3)On-Going₱23.9M
25OD0376Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 180, CALOOCAN CITYOn-Going₱28.6M
25OD0368Jul 21, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 153, CALOOCAN CITYOn-Going₱28.7M
25OD0360Jul 9, 2025CONSTRUCTION (COMPLETION) PUP NORTH CALOOCAN CITY CAMPUS ACADEMIC BUILDING INCLUDING GROUND IMPROVEMENT (PHASE 6), BRGY. 168, CALOOCAN CITYOn-Going₱139.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.