Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 15CK0114

DPWH infrastructure contract
Contract ID:
15CK0114
Fingerprint:
ebbb5acc06f1ef…903cad72f1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 25, 2016 (10 yrs 9 mo ago) · Target/actual end Jun 21, 2016
Description:
NETWORK DEVELOPMENT, WIDENING OF NATIONAL ROADS ALONG CONCEPCION-LAPAZ ROAD, LAPAZ, TARLAC
Category:
Roads
Implementing office:
DPWH Tarlac 2nd DEO · Region III
Contractor:
Contract amount:
₱45,091,819.47 (₱45.1M)
Funding source:
Regular Infra - GAA 2016 MFO-1
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
e8b284ca0525…Jan 7, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC 2ND-DEO₱45,091,819.36

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CK0082Jun 13, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG THE BANKS OF RIO CHICO RIVER IN BARANGAY LOMBOY (PHASE VII), LA PAZ, TARLACCompleted₱94.7M
25CK0119May 20, 2025CONSTRUCTION OF SCHOOL BUILDING, LAPURISIMA INTEGRATED SCHOOL, LA PAZ, TARLACCompleted₱9.7M
25CK0089Apr 3, 2025REHABILITATION OF ROAD, BARANGAY DUMARAIS - BALANOY, PHASE 1, LA PAZ, TARLACCompleted₱96.5M
25CK0118Apr 3, 2025REHABILITATION OF ROAD AT BARANGAY SAN ROQUE, LA PAZ, TARLACCompleted₱49.0M
25CK0005Mar 25, 2025NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - TERTIARY ROADS ALONG VICTORIA - LA PAZ ROAD, K0135 + 075.00 - K0135 + 500.00, LA PAZ, TARLACCompleted₱18.8M
25CK0007Mar 25, 2025ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS ALONG VICTORIA - LA PAZ ROAD, LA PAZ, TARLACOn-Going₱48.0M
25CK0013Mar 25, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (PHASE I), LA PAZ, TARLACOn-Going₱69.8M
25CK0014Mar 25, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (PHASE II), LA PAZ, TARLACOn-Going₱72.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.