Project 15CN0131
DPWH infrastructure contract
Contract ID:
15CN0131
Fingerprint:
38f6e5a37cb9a7…23aa4b6b8c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 16, 2016 (10 yrs 9 mo ago) · Target/actual end May 25, 2016
Description:
REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, CEMENTO BR. (B02836LZ) ALONG BALER-CEMENTO ROAD VIA DICALOYUNGAN
Category:
Bridges
Implementing office:
DPWH Aurora DEO · Region III
Contractor:
R.N.G.M. CONSTRUCTION CORPORATION (FORMERLY: R.N.G.M. CONSTRUCTION) · DPWH contractor code 20281
Contract amount:
₱4,722,158.67 (₱4.7M)
Funding source:
Regular Infra - GAA 2016 MFO-1
Budget year:
2016
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CN0157 | Sep 1, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING , BARANGAY ZABALI, BALER, AURORA | On-Going | ₱99.0M |
| 25CN0166 | Aug 27, 2025 | CONSTRUCTION OF ROAD (PHASE 2), BARANGAY ZABALI, BALER, AURORA | Terminated | ₱0 |
| 25CN0096 | Aug 4, 2025 | CONSTRUCTION OF ROAD, BARANGAY ZABALI, BALER, AURORA | Completed | ₱28.9M |
| 25CN0168 | Jul 18, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), BARANGAY CALABUANAN, BALER, AURORA | On-Going | ₱4.8M |
| 25CN0116 | Jul 7, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY RESERVA, BALER, AURORA | On-Going | ₱6.9M |
| 25CN0182 | Jul 3, 2025 | RAINWATER COLLECTOR SYSTEM | On-Going | ₱2.6M |
| 25CN0150 | Jun 10, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SABANG, BALER, AURORA | On-Going | ₱4.9M |
| 25CN0021 | May 28, 2025 | REPLACEMENT OF PERMANENT WEAK BRIDGES, PUDOC BR. (B03014LZ) ALONG BALER - CASIGURAN RD (BALER - DINADIAWAN) | On-Going | ₱65.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.