Project 15DB0126
DPWH infrastructure contract
Contract ID:
15DB0126
Fingerprint:
632a792ec69bc1…3f2bc22ffe Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 3, 2016 (10 yrs 9 mo ago) · Target/actual end Mar 18, 2016
Description:
CONCRETING OF ROADS (POB. 3, BRGY. GULOD, BRGY. QUILITISAN, BRGY. BALIBAGO) CALATAGAN, BATANGAS
Category:
Roads
Implementing office:
DPWH Batangas 1st DEO · Region IV-A
Contractor:
JUBER CONSTRUCTION · DPWH contractor code 14463
Location:
Contract amount:
₱1,933,194.00 (₱1.9M)
Funding source:
Regular Infra - GAA 2016 Locally Funded Projects
Budget year:
2016