Physical progress:
100%
Timeline:
Start Apr 14, 2016 (10 yrs 7 mo ago) · Target/actual end Jun 12, 2016
Description:
REHABILITATION/CONSTRUCTION OF SLOPE PROTECTION ALONG MSR JCT. LOPEZ-CATANAUAN ROAD K0241+016-K0241+044
Category:
Roads
Implementing office:
DPWH Quezon 3rd DEO · Region IV-A
Contractor:
KKT CONSTRUCTION AND SUPPLY · DPWH contractor code 36852
Contract amount:
₱2,243,823.55 (₱2.2M)
Funding source:
Regular Infra - GAA 2016 MFO-1
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
5f853d7485e7…Jan 18, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - QUEZON 3RD ED₱2,243,823.55

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DM0176Jan 14, 2026CONSTRUCTION OF CLASSROOMS, MABINI ES, UNISAN, QUEZONOn-Going₱9.4M
25DM0182Jan 14, 2026CONSTRUCTION OF CLASSROOMS, UNISAN CENTRAL ELEMENTARY SCHOOL, UNISAN, QUEZONOn-Going₱5.0M
25DM0188Jan 12, 2026CONSTRUCTION OF SHOOL HEALTH FACILITIES, CATANAUAN CS, CATANAUAN, QUEZONCompleted₱4.8M
25DM0151Aug 18, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BONDOC PENINSULA DISTRICT HOSPITAL, CATANAUAN, QUEZONOn-Going₱93.5M
25DM0077Jun 30, 2025CONSTRUCTION OF ROAD, SITIO PIER, BARANGAY SAN ANTONIO PALA, MUNICIPALITY OF CATANAUAN, QUEZONCompleted₱9.6M
25DM0138Jun 30, 2025CONSTRUCTION OF FLOOD MITIGATION, STRUCTURE ALONG BINGABING CREEK, BRGY. MADULAO, CATANAUAN, QUEZONOn-Going₱48.5M
25DM0144Jun 30, 2025CONSTRUCTION OF BRGY BOLO ROAD, CATANAUAN, QUEZONCompleted₱24.2M
25DM0147Jun 30, 2025CONSTRUCTION OF DRAINAGE SYSTEM, BRGY. MADULAO, CATANAUAN, QUEZONOn-Going₱48.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.