Project 15DO0126

DPWH infrastructure contract
Contract ID:
15DO0126
Fingerprint:
c3d0493b9bd8f0…d081020f6d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 7, 2016 (10 yrs 9 mo ago) · Target/actual end Jan 22, 2018
Description:
MFO 1-NATIONAL ROAD NETWORK SERVICES-NETWORK DEVELOPMENT-OFF-CARRIAGEWAY IPROVEMENT INCLUDING DRAINAGE OF PILILLA JUNCTION-JALAJALA ROAD (S01582LZ) K0062+(-575)-K0062+124, K0074+000-K0075+920, PILILLA AND JALAJALA RIZAL
Category:
Flood Control/Hydraulics/Drainage, Roads: Rehabilitation - PCCP
Implementing office:
DPWH Rizal 2nd DEO · Region IV-A
Contractor:
HALREY CONSTRUCTION INC. · DPWH contractor code 2267
Contract amount:
₱39,641,508.99 (₱39.6M)
Funding source:
Regular Infra - Flood Control/Hydraulics/Drainage, Roads: Rehabilitation - PCCP
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
558b3424ec7e…Jan 21, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - RIZAL II DEO₱36,829,968.66

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DO0035Apr 2, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - MANILA EAST RD - K0064 + 000 - K0064 + 170On-Going₱4.3M
25DO0052Apr 2, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - MANILA EAST RD - K0064+450 - K0064+700Completed₱38.9M
25DO0087Mar 12, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY HALAYHAYIN, PILILLA, RIZALOn-Going₱4.8M
25DO0102Mar 12, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-WIDENING OF PERMANENT BRIDGES-PILILLA BR. 2 (B02858LZ) ALONG SAGBAT-PILILLA DIV RDOn-Going₱18.2M
25DO0001Feb 13, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - MANILA EAST RD - K0068 + 820 - K0069 + 278Completed₱18.0M
25DO0028Feb 13, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, SITIO BCompleted₱4.8M
24DO0044Jul 15, 2024ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - MANILA EAST RD - K0056+854 - K0057+200On-Going₱14.1M
24DO0090Mar 25, 2024ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - MANILA EAST ROAD, K0058+300 - K0058+920Completed₱77.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.