FY2026 GAA: ₱6.79T
PisoScan

Project 15IB0284

DPWH infrastructure contract
Contract ID:
15IB0284
Fingerprint:
20d41d73a37423…7cb88f6b19 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 10, 2016 (10 yrs 9 mo ago) · Target/actual end Jun 8, 2016
Description:
CONCRETIING OF BRGY. ROAD (BRGY. COGON ROAD LEADING TO EVACUATION CENTER) GUIUAN, EASTERN SAMAR
Category:
Roads
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
A.C. RIVERO DEVELOPMENT CORPORATION · DPWH contractor code 5122
Contract amount:
₱9,480,447.97 (₱9.5M)
Funding source:
Regular Infra - GAA 2016 Locally Funded Projects
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
88b70dd4bbb7…Jan 11, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - EASTERN SAMAR DEO₱9,480,447.97

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.