Project 15IG0187
DPWH infrastructure contract
Contract ID:
15IG0187
Fingerprint:
c95f41be2b865e…8830f69f44 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 5, 2016 (10 yrs 9 mo ago) · Target/actual end Apr 4, 2016
Description:
REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, MALASIGA BR. (B00632LT) ALONG ABUYOG - SILAGO ROAD
Category:
Bridges
Implementing office:
DPWH Leyte 5th DEO · Region VIII
Contractor:
R. AGULLO CONSTRUCTION & ENTERPRISES · DPWH contractor code 33728
Contract amount:
₱1,654,703.11 (₱1.7M)
Funding source:
Regular Infra - GAA 2016 MFO-1
Budget year:
2016
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IG0090 | May 12, 2026 | CONSTRUCTION OF ONE (1) STOREY - THREE (3) CLASSROOMS SCHOOL BUILDING, MATAGNAO PRIMARY SCHOOL, BARANGAY MATAGNAO, ABUYOG, LEYTE | On-Going | ₱15.7M |
| 25IG0082 | Sep 18, 2025 | CONSTRUCTION OF SCHOOL BUILDING (PHASE 2), CANMARATING NATIONAL HIGH SCHOOL, BARANGAY CANMARATING, ABUYOG, LEYTE | Completed | ₱5.0M |
| 25IG0053 | Jul 1, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BITO, ABUYOG, LEYTE | On-Going | ₱4.9M |
| 25I00060 | Jun 13, 2025 | NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY - K0975+155 - K0976+000, K0991+900 - K0992+657, K0996+148.6 - K0996+155, K0997+455 - K0997+610 | On-Going | ₱65.5M |
| 25IG0026 | Jun 3, 2025 | CONSTRUCTION OF ROAD, BARANGAY PICAS SUR, ABUYOG, LEYTE | Completed | ₱4.9M |
| 25IG0049 | Jun 3, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN ISIDRO, ABUYOG, LEYTE | Completed | ₱3.0M |
| 25IG0007 | May 20, 2025 | CONSTRUCTION OF ROAD, BARANGAY ODIONGAN, ABUYOG, LEYTE | Completed | ₱4.9M |
| 25IG0035 | May 20, 2025 | ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - ABUYOG-SILAGO RD - K0984 + 000 - K0984 + 350 | Completed | ₱8.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.