Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 15K00116

DPWH infrastructure contract
Contract ID:
15K00116
Fingerprint:
293ff3518af2da…134d5aeeb0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 7, 2016 (10 yrs 8 mo ago) · Target/actual end Dec 24, 2016
Description:
WIDENING OF ALUBIJID BR(B00325MN)ALONG BCIR,MIS. OR. 2ND LD
Category:
Bridges-Construction-Concrete, Roads: Construction - PCCP
Implementing office:
DPWH Region X · Region X
Location:
Not stated in the source
Contract amount:
₱85,800,000.00 (₱85.8M)
Funding source:
Regular Infra - Bridges-Construction-Concrete, Roads: Construction - PCCP
Budget year:
2016