Project 15K00500
DPWH infrastructure contract
Contract ID:
15K00500
Fingerprint:
c48c4f7859af81…bdf83b2fd0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 11, 2016 (10 yrs 7 mo ago) · Target/actual end Jun 15, 2016
Description:
CLUSTER'N'-CONC./REHAB.OF VARIOUS LOCAL RDS IN BUTIG,LDS 11
Category:
GAA 2016 Locally Funded Projects
Implementing office:
DPWH Region X · Region X
Contractor:
FFJJ CONSTRUCTION · DPWH contractor code 16712
Contract amount:
₱13,034,025.69 (₱13.0M)
Funding source:
Regular Infra - GAA 2016 Locally Funded Projects
Budget year:
2016
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 29a14f0112b7… | Feb 16, 2016 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION X | ₱13,034,035.08 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25K00080 | Apr 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANDAB, BUTIG, LANAO DEL SUR | On-Going | ₱7.4M |
| 25K00098 | Apr 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY RAYA, BUTIG, LANAO DEL SUR | On-Going | ₱7.4M |
| 25K00189 | Mar 10, 2025 | CONSTRUCTION OF DRAINAGE STRUCTURE, BUTIG, LANAO DEL SUR | On-Going | ₱9.9M |
| 24K00446 | Aug 30, 2024 | REHABILITATION OF MULTI-PURPOSE BUILDING, DIANATON NAIM GYMNASIUM, BRGY. BAYABAO POBLACION, MUNICIPALITY OF BUTIG, LANAO DEL SUR | On-Going | ₱9.9M |
| 21K00342 | Nov 22, 2021 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POKTAN, BUTIG, LANAO DEL SUR | Completed | ₱1.9M |
| 21K00343 | Nov 22, 2021 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TIOWI, BUTIG, LANAO DEL SUR | Completed | ₱1.8M |
| 21K00346 | Nov 8, 2021 | CONSTRUCTION/IMPROVEMENT OF MULTI-PURPOSE BUILDING (PUBLIC MARKET) IN BRGY. BAYABAO POBLACION, BUTIG, LANAO DEL SUR | Completed | ₱4.9M |
| 21K00336 | Oct 22, 2021 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BAYABAO POBLACION, BUTIG, LANAO DEL SUR | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.