Project 15KJ0118

DPWH infrastructure contract
Contract ID:
15KJ0118
Fingerprint:
27c3f2f7f9c8e9…5ddac7fd74 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 25, 2016 (10 yrs 7 mo ago) · Target/actual end May 2, 2016
Description:
CONCRETING OF BARANGAY ROAD, BARANGAY DELA PAZ, CLARIN, MISAMIS OCCIDENTAL
Category:
Roads
Implementing office:
Contractor:
3R'S BUILDERS AND RESOURCES · DPWH contractor code 35922
Contract amount:
₱1,942,998.32 (₱1.9M)
Funding source:
Regular Infra - GAA 2016 Locally Funded Projects
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
786c77920a5b…Feb 29, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MIS. OCC. SUB-DEO₱1,942,998.32

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.