FY2026 GAA: ₱6.79T
PisoScan

Project 15L00087

DPWH infrastructure contract
Contract ID:
15L00087
Fingerprint:
f968672495e932…cb10b72e75 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 9, 2016 (10 yrs 8 mo ago) · Target/actual end Jun 14, 2018
Description:
WIDENING OF DIGOS-MAKAR ROAD INCLUDING ROAD RIGHT-OF-WAY (RROW),NEW BACLAYON-TAGANSULE SECT.,DAVAO D
Category:
Roads
Implementing office:
DPWH Region XI · Region XI
Contractor:
THREE W BUILDERS, INC. · DPWH contractor code 10722
Contract amount:
₱96,322,908.56 (₱96.3M)
Funding source:
Regular Infra - GAA 2016 MFO-1
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
41ecd965f2f5…Feb 4, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION XI₱96,990,996.07

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25L00126Sep 12, 2025CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - MAHARLIKA HIGHWAY (DIGOS - MAKAR RD.) - K1589+861 - K1569+903, K1590+000 - K1590+224, DAVAO DEL SUROn-Going₱97.3M
25LD0173Jun 25, 2025CONSTRUCTION OF FLOOD MITIGATING STRUCTURE (CONCRETE REVETMENT/DIKE) ALONG MALALAG RIVER( STEEL BRIDGE, PUROK 2 & PUROK 3 SECTION), BRGY. IBO, MALALAG, DAVAO DEL SUROn-Going₱96.0M
25LD0146Jun 9, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE-CONCRETE REVETMENT ALONG PADADA-MAINIT RIVER (LAPULABAO-MASALAM BRIDGE DOWNSTREAM SECTION) HAGONOY, DAVAO DEL SURCompleted₱120.0M
25ME0009Mar 31, 2025NHW JCT. MALUNGON GAMAY - KIBAWALAN - PUROK ONSE LEADING TO BUSAGAN FALLS, MALUNGON, SARANGANI PROVINCECompleted₱9.5M
25LD0207Mar 26, 2025CONCRETING OF BRGY. BULACAN FMR, BRGY. BULACAN, MALALAG, DAVAO DEL SURCompleted₱14.4M
25LD0065Mar 24, 2025CONSTRUCTION OF FLOOD MITIGATING STRUCTURE ALONG MALALAG RIVER (IBO-PITO SECTION), BARANGAY IBO, MALALAG, DAVAO DEL SUROn-Going₱47.5M
25LD0071Mar 24, 2025PREVENTIVE MAINTENANCE OF ROAD; ASPHALT OVERLAY- DAVAO- SARANGANI COASTAL RD ( MALALAG- MALITA-JAS-G)- K1595+445-K1596+042, DAVAO DEL SUROn-Going₱24.9M
25LD0081Mar 24, 2025CONSTRUCTION (COMPLETION) OF MPB, BRGY. BOLTON, MALALAG, DAVAO DEL SURCompleted₱3.0M