Project 15M00112
DPWH infrastructure contract
Contract ID:
15M00112
Fingerprint:
65c0ee35f605b6…d832d29106 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 26, 2016 (10 yrs 8 mo ago) · Target/actual end Oct 15, 2016
Description:
ROAD UPGRADING (UNPAVED TO PAVED) OF MATALAM-LAMPAYAN-ANTIPAS ROAD, K1663+687.36-K1668+658; K1668+658-K1670+260 MATALAM, NORTH COTABATO
Category:
GAA 2016 MFO-1
Implementing office:
DPWH Region XII · Region XII
Contractor:
ALZEN ENGINEERING & CONSTRUCTION SUPPLIES (13911) / BORDERLINE CONSTRUCTION & SUPPLY · DPWH contractor code 24433
Location:
Not stated in the source
Contract amount:
₱146,055,220.98 (₱146.1M)
Funding source:
Regular Infra - GAA 2016 MFO-1
Budget year:
2016
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.