Project 15M00126
DPWH infrastructure contract
Contract ID:
15M00126
Fingerprint:
725e63c609dc78…777a5f002d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 25, 2016 (10 yrs 3 mo ago) · Target/actual end Jan 10, 2019
Description:
CONSTRUCTION OF MIWAROY BRIDGE ALONG COTABTO CITY CIRCUMFERENTIAL (WESTERN SECTION), COTABATO CITY
Category:
Bridges
Implementing office:
DPWH Region XII · Region XII
Contractor:
GRACE CONSTRUCTION CORPORATION · DPWH contractor code 3771
Location:
Not stated in the source
Contract amount:
₱138,820,019.41 (₱138.8M)
Funding source:
Regular Infra - GAA 2016 MFO-1
Budget year:
2016
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 188bd6cdaae1… | Mar 25, 2016 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION XII | ₱138,847,666.33 |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.