Project 15OB0385

DPWH infrastructure contract
Contract ID:
15OB0385
Fingerprint:
9c52aad97e519b…0155ed69c2 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 4, 2016 (10 yrs 9 mo ago) · Target/actual end Feb 22, 2016
Description:
PREVENTIVE MAINTENANCE OF BONI AVENUE, MANDALUYONG CITY, (WESTBOUND) K0011+(-428) TO K0011+219
Category:
Roads
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
B. BERNARDO CONST., INC. · DPWH contractor code 6196
Contract amount:
₱6,548,165.61 (₱6.5M)
Funding source:
Regular Infra - GAA 2016 MFO-1
Budget year:
2016

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25OB0310Jun 20, 2025CONSTRUCTION (COMPLETION) OF SENATE PRESIDENT NEPTALI GONZALES GENERAL HOSPITAL AT BARANGAY MAUWAY PACKAGE 7, MANDALUYONG CITYCompleted₱94.5M
25OB0341May 20, 2025CONSTRUCTION OF MULTI LEVEL PURPOSE BUILDING, PACKAGE 2, BARANGAY DAANG BAKAL, MANDALUYONG CITYOn-Going₱19.4M
25OB0342May 20, 2025CONSTRUCTION OF MULTI LEVEL PURPOSE BUILDING, PACKAGE 2, BARANGAY HARAPIN ANG BUKAS, MANDALUYONG CITYCompleted₱19.4M
25OB0343May 20, 2025CONSTRUCTION OF MULTI PURPOSE BUILDING (BARANGAY HALL) ANNEX, BARANGAY ADDITION HILLS, MANDALUYONG CITYOn-Going₱29.1M
25OB0344May 20, 2025CONSTRUCTION OF MULTI PURPOSE BUILDING (NEAR ACTIVITY CENTER), NATIONAL CENTER FOR MENTAL HEALTH, MANDALUYONG CITYCompleted₱19.4M
25OB0348May 20, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE INCLUDING UPRADING OF ELECTRICAL FACILITIES AT SANCTUARY DOH NCR PHASE 2, BARANGAY ADDITION HILLS, MANDALUYONG CITYCompleted₱14.6M
25OB0353May 20, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY WACKWACK PACKAGE 7, MANDALUYONG CITYCompleted₱97.0M
25OB0354May 20, 2025CONSTRUCTION (COMPLETION) OF MULTI LEVEL BUILDING AT ANDRES BONIFACIO INTEGRATED SCHOOL, MANDALUYONG CITYTerminated₱2.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.