Project 15OB0495
DPWH infrastructure contract
Contract ID:
15OB0495
Fingerprint:
0aeb18e78d4da7…63068a320e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 1, 2016 (10 yrs 8 mo ago) · Target/actual end Aug 12, 2017
Description:
IMPROVEMENT/REHABILITATION OF DRAINAGE SYSTEM ALONG M.H. DEL PILAR STREET, BRGY. PALATIW, PASIG CITY
Category:
Flood Control and Drainage
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
M.S. RAMOS CONSTRUCTION INC. (FORMERLY: M.S. RAMOS · DPWH contractor code 31684
Contract amount:
₱8,685,227.06 (₱8.7M)
Funding source:
Regular Infra - GAA 2016 MFO-2
Budget year:
2016
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25OB0443 | Jul 13, 2026 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. NEW LOWER BICUTAN, TAGUIG CITY (PHASE 1) | On-Going | ₱46.9M |
| 25OB0367 | Apr 15, 2026 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AND SITE DEVELOPMENT AT LAKESHORE AT BARANGAY LOWER BICUTAN, TAGUIG CITY | On-Going | ₱47.0M |
| 25OB0409 | Aug 14, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, NRCPO, CAMP BAGONG DIWA, TAGUIG CITY | On-Going | ₱29.1M |
| 25OB0437 | Aug 14, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SPD COMPOUND, LAWTON AVE., BARANGAY WESTERN BICUTAN, TAGUIG CITY (PHASE 1) | On-Going | ₱48.5M |
| 25OC0178 | Jul 8, 2025 | REHABILITATION/IMPROVEMENT OF SOUTH SUPER H-WAY WEST SERVICE RD (S03387LZ)(INTERMITTENT) PARAÑAQUE CITY, METRO MANILA | Completed | ₱12.8M |
| 25OB0371 | Jun 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 1) | On-Going | ₱48.5M |
| 25OB0372 | Jun 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 2) | On-Going | ₱48.5M |
| 25OB0373 | Jun 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 5) | On-Going | ₱72.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.