Project 16AD0149
DPWH infrastructure contract
Contract ID:
16AD0149
Fingerprint:
2b19f038ab24b9…444222a8d8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 25, 2017 (9 yrs 5 mo ago) · Target/actual end May 17, 2018
Description:
REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGED BASED ON PAVEMENT MANAGEMENT-4(HDM-4), JCT. STA. LUCIA-SALCEDO ROAD, K0340+000-K0341+000 AND K0341+918-K0342+000
Category:
Roads
Implementing office:
DPWH Ilocos Sur 2nd DEO · Region I
Contractor:
R.S. SEPIAN CONSTRUCTION & TRUCKING · DPWH contractor code 20519
Contract amount:
₱31,276,488.42 (₱31.3M)
Funding source:
Regular Infra - GAA 2017 MFO-1
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 28a2cf213b52… | May 8, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOCOS SUR 2ND DEO | ₱29,413,356.63 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25A00124 | Apr 7, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY BANI, SANTA LUCIA, ILOCOS SUR | On-Going | ₱9.6M |
| 25AD0016 | Feb 14, 2025 | BIP-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES - CONSTRUCTION OF VICAL-SABUANAN SEAWALL, BARANGAY VICAL AND BARANGAY SABUANAN, SANTA, LUCIA, ILOCOS SUR | Completed | ₱38.4M |
| 25AD0027 | Feb 10, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SANTA LUCIA, ILOCOS SUR | Completed | ₱9.6M |
| 24AD0085 | May 3, 2024 | CONSTRUCTION OF REINFORCED CONSTRUCTION BRIDGE ALONG STA. LUCIA-SALCEDO ROAD, STA. LUCIA, ILOCOS SUR | Completed | ₱19.3M |
| 24AD0043 | Apr 12, 2024 | CONSTRUCTION OF ROAD, PALALI-NORTE-PALACAPAC ROAD, SANTA LUCIA, ILOCOS SUR | Completed | ₱14.7M |
| 24AD0025 | Feb 28, 2024 | FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF LUBA SEAWALL, SANTA LUCIA, ILOCOS SUR | Completed | ₱39.2M |
| 23AD0055 | Jun 30, 2023 | CONSTRUCTION OF SOLAR WATER SYSTEM, STA LUCIA, ILOCOS SUR | Completed | ₱9.5M |
| 23AD0087 | Mar 24, 2023 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BARANGOBONG, SANTA LUCIA, ILOCOS SUR | Completed | ₱4.9M |