Project 16AH0158
DPWH infrastructure contract
Contract ID:
16AH0158
Fingerprint:
f8e242c08f944d…96e6fc9c8e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 27, 2016 (10 yrs 4 mo ago) · Target/actual end Jan 10, 2018
Description:
CONST'N.OF TWO(2)UNITS,FOUR(4)STOREY,SIXTEEN(16)CL,SB(DEPED DESIGN)AT BASISTA NHS,BASISTA,PANGASINAN
Category:
Buildings and Facilities
Implementing office:
DPWH Pangasinan 2nd DEO · Region I
Contractor:
STO. CRISTO CONSTRUCTION & TRADING INC. (FOR: STO. CRISTO CONSTRUCTION & TRADING) · DPWH contractor code 26096
Contract amount:
₱52,651,816.46 (₱52.7M)
Funding source:
Outside Infra - GAA 2016 DepED BEFF
Budget year:
2016
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AH0153 | Jun 11, 2025 | IMPROVEMENT OF ROADS, BASISTA, PANGASINAN | Completed | ₱46.0M |
| 25AH0177 | Mar 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PLAZA OF BARANGAY DUMPAY, BASISTA, PANGASINAN | On-Going | ₱4.7M |
| 25AH0115 | Mar 17, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING(MUNICIPAL TOWN HALL),PHASE II,BRGY. POBLACION,BASISTA,PANGA | On-Going | ₱29.1M |
| 25AH0110 | Feb 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL),BARANGAY DUMPAY, BASISTA, PANGASINAN | On-Going | ₱7.8M |
| 24AH0106 | Oct 3, 2024 | REHABILITATION OF MUNICIPAL TOWN HALL BUILDING, POBLACION, BASISTA, PANGASINAN | On-Going | ₱7.8M |
| 24A00576 | Sep 9, 2024 | COMPLETION/EQUIPPING OF SUPER HEALTH CENTERS - BASISTA SUPER HEALTH CENTER, PANGASINAN | On-Going | ₱6.0M |
| 24AH0135 | May 29, 2024 | RENOVATION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL) IN BARANGAY POBLACION, BASISTA, PANGASINAN | Completed | ₱9.9M |
| 24AH0084 | Mar 15, 2024 | WIDENING OF PERMANENT BRIDGES AT PALMA BR.(B02766LZ)ALONG CARMEN JCT.-BAYAMBANG-MANAT RD.(PHASE II)B | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.