Project 16AJ0100
DPWH infrastructure contract
Contract ID:
16AJ0100
Fingerprint:
60d5f40409c11f…c54fb44450 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 19, 2016 (9 yrs 10 mo ago) · Target/actual end Dec 28, 2016
Description:
CONSTRUCTION OF DPWH MATERIALS RECOVERY FACILITY, DPWH PANGASINAN IV DEO, STA. BARBARA, PANGASINAN
Category:
Buildings and Facilities
Implementing office:
DPWH Pangasinan 4th DEO · Region I
Contractor:
MCB CONSTRUCTION & SUPPLY · DPWH contractor code 12128
Location:
Contract amount:
₱151,493.79 (₱151.5K)
Funding source:
Regular Infra - GAA 2016 Locally Funded Projects
Budget year:
2016
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.