Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 16BE0161

DPWH infrastructure contract
Contract ID:
16BE0161
Fingerprint:
36686bbf7fcfad…66a5386496 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 4, 2017 (9 yrs 10 mo ago) · Target/actual end Mar 4, 2017
Description:
BALASIG BIRTHING CENTER, CABAGAN, ISABELA (UPGRADING OF EXISTING FACILITY) CABAGAN, ISABELA
Category:
Buildings and Facilities
Implementing office:
Contractor:
FRAGERR CONSTRUCTION · DPWH contractor code 12722
Contract amount:
₱963,871.19 (₱963.9K)
Funding source:
Outside Infra - GAA 2016 DOH HFEP
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
fe45b87cafd9…Dec 19, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 1ST DEO₱963,871.19

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25BE0168Jun 17, 2026CONSTRUCTION OF CLASSROOMS, CANDANUM INTEGRATED SCHOOL, CABAGAN, ISABELAOn-Going₱28.5M
25BE0143Jan 22, 2026CONCRETING OF SITIO PELO, BRGY. CANSAN FMR, BRGY. CANSAN, CABAGAN, ISABELAOn-Going₱14.5M
25BE0131Sep 16, 2025CONSTRUCTION OF SCHOOL BUILDING, CUBAG INTEGRATED SCHOOL, BARANGAY CUBAG, CABAGAN, ISABELACompleted₱19.3M
24BE0183Aug 20, 2025CONSTRUCTION OF SEWAGE TREATMENT PLANT, MILAGROS ALBANO DISTRICT HOSPITAL, CABAGAN, ISABELA BARANGAY NGARAG, CABAGAN, ISABELAOn-Going₱28.1M
25BE0078Jul 14, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY AGGUB, CABAGAN, ISABELAOn-Going₱9.6M
25BE0082Jul 14, 2025CONCRETING OF MALASI-SAN ANTONIO FMR, BRGY. SITIO MALASI, BRGY. SAN ANTONIO, CABAGAN, ISABELAOn-Going₱14.5M
25BE0089Jul 14, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG CAGAYANOn-Going₱140.3M
25BE0090Jul 14, 2025ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRUCTUROn-Going₱93.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.