Project 16CE0018
DPWH infrastructure contract
Contract ID:
16CE0018
Fingerprint:
f1b284ca6415a0…5125dd6085 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 30, 2016 (10 yrs 7 mo ago) · Target/actual end May 28, 2016
Description:
CONCRETING OF LOOB-PIGLISAN FMR, BRGY. LOOB - PIGLISAN, CUYAPO, NUEVA ECIJA
Category:
Roads
Implementing office:
DPWH Nueva Ecija 1st DEO · Region III
Contractor:
GREENWALL CONSTRUCTION · DPWH contractor code 14457
Location:
Contract amount:
₱1,920,429.25 (₱1.9M)
Funding source:
Outside Infra - GAA 2016 DA Farm-to-Market Roads
Budget year:
2016
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| a1cc34a84692… | Mar 21, 2016 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - N. ECIJA 1ST DEO | ₱1,920,429.25 |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.